Question 1,278 of 1,731
People: organizations, teams, and leadershipmediumMultiple SelectObjective-mapped

Quick Answer

The answer is managing the project within tolerances set by the Project Board. This is correct because the Project Manager is the day-to-day leader who must deliver the project’s products while staying within the agreed cost, time, scope, risk, and quality tolerances delegated by the Project Board; exceeding these tolerances requires an exception report and escalation. On the PRINCE2 Foundation exam, this responsibility tests your understanding of the management-by-exception principle, where the Project Manager operates autonomously within defined boundaries. A common trap is confusing the Project Manager’s role with the Project Board’s strategic oversight—remember that the Board sets tolerances, but the Manager works within them. For a memory tip, think “Tolerances are the fence; the Manager plays inside the yard.”

PRINCE2F People: organizations, teams, and leadership Practice Question

This PRINCE2F practice question tests your understanding of people: organizations, teams, and leadership. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO of the following are responsibilities of the Project Manager?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Preparing Stage Plans

A is correct because the Project Manager is responsible for preparing Stage Plans, which detail how the work for a management stage will be executed, including schedules, resources, and controls. This is a core PRINCE2 responsibility as the Project Manager translates the Project Plan into actionable Stage Plans for the Project Board's approval.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Preparing Stage Plans

    Why this is correct

    The Project Manager prepares Stage Plans.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Providing independent assurance to the Project Board

    Why it's wrong here

    This is Project Assurance.

  • Updating the Business Case

    Why it's wrong here

    The SRO maintains the Business Case.

  • Approving Stage Plans

    Why it's wrong here

    Approval is done by the Project Board.

  • Managing the project within tolerances set by the Project Board

    Why this is correct

    Day-to-day management within tolerances is a key PM responsibility.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is confusing the Project Manager's role in preparing Stage Plans with the Project Board's role in approving them, or mistaking the Project Manager for the owner of the Business Case, which is a common PRINCE2 Foundation exam pitfall.

Detailed technical explanation

How to think about this question

In PRINCE2, the Project Manager operates within delegated tolerances from the Project Board, managing the stage to deliver products as defined in the Stage Plan. The Project Manager escalates any forecasted deviations beyond tolerances to the Project Board via an Exception Report, ensuring the board retains control over major changes. This separation of preparation (Project Manager) and approval (Project Board) is a key governance mechanism in the PRINCE2 process model.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

People: organizations, teams, and leadership — This question tests People: organizations, teams, and leadership — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Preparing Stage Plans — A is correct because the Project Manager is responsible for preparing Stage Plans, which detail how the work for a management stage will be executed, including schedules, resources, and controls. This is a core PRINCE2 responsibility as the Project Manager translates the Project Plan into actionable Stage Plans for the Project Board's approval.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are responsibilities of the Project Manager?

medium
  • A.Create the Project Initiation Documentation
  • B.Prepare the Highlight Report for the Project Board
  • C.Manage the project on a day-to-day basis
  • D.Authorize Work Packages
  • E.Provide independent assurance to the Project Board

Why B: The Project Manager manages day-to-day operations and prepares Highlight Reports. Creating the PID is done in Initiating a Project, and authorizing Work Packages is the Team Manager's role.

Variation 2. Which TWO of the following are responsibilities of the Project Manager?

medium
  • A.Prepare the Stage Plan for approval by the Project Board
  • B.Provide independent assurance
  • C.Manage the project within tolerances
  • D.Approve the Project Initiation Documentation
  • E.Chair the Project Board meetings

Why A: Option A is correct because the Project Manager is responsible for preparing Stage Plans, which detail how a management stage will be executed, and submitting them to the Project Board for approval. This aligns with PRINCE2's principle of management by stages, where the Project Manager provides the detailed plan for the next stage.

Variation 3. Which of the following is NOT a responsibility of the Project Manager?

medium
  • A.Preparing Highlight Reports for the Project Board
  • B.Performing Project Assurance
  • C.Authorizing work packages for the Team Manager
  • D.Managing the project within tolerances

Why B: Project Assurance is independent and cannot be delegated to the Project Manager.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.