PRINCE2 PracticesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which THREE of the following are outputs of the Initiating a Project process?

⚠ Common exam trap

Candidates often confuse outputs from the Initiating a Project process with those from later processes like Controlling a Stage or Closing a Project, leading candidates to select Highlight Report or Lessons Report.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Business Case (updated)

The Initiating a Project process updates the Business Case to reflect the detailed understanding of the project's justification, costs, benefits, and risks gained during initiation. This updated Business Case is a key output that confirms whether the project remains viable before proceeding.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Business Case (updated)

    Why this is correct

    The Business Case is updated and approved in IP.

  • Project Plan

    Why this is correct

    The Project Plan is created during Initiating a Project.

  • Highlight Report

    Why it's wrong here

    Highlight Reports are produced during Controlling a Stage.

  • Risk Management Approach

    Why this is correct

    Management approaches are defined in IP.

  • Lessons Report

    Why it's wrong here

    The Lessons Report is produced during the Managing a Stage Boundary process, not Initiating a Project, which instead outputs the Project Initiation Documentation. It is tempting because lessons are captured throughout the project, and a preliminary Lessons Log is created during Starting Up a Project; however, the formalised Lessons Report is only drafted at the end of each stage and finalised in the Closing a Project process.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which of the following is a key output of the Initiating a Project process?

medium
  • A.Project Brief
  • B.Stage Plan
  • C.Project Initiation Documentation
  • D.Benefits Management Approach

Why C: The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It provides a comprehensive baseline that defines the project's scope, objectives, risks, and controls. Option A (Project Brief) is an input to the process, not an output. Option B (Stage Plan) is created during the Managing a Stage Boundary process. Option D (Benefits Management Approach) is developed during the Initiating a Project process but is part of the PID, not a separate key output. The PID itself is the primary output that brings together all the management products required to initiate the project.

Variation 2. Which TWO of the following are outputs of the Initiating a Project process?

medium
  • A.Project Plan
  • B.End Stage Report
  • C.Business Case
  • D.Work Package
  • E.Highlight Report

Why A: The Project Plan is a key output of the Initiating a Project process. This process refines the outline Business Case and creates a detailed, baselined Project Plan that defines how the project will deliver its products within agreed tolerances. The Project Plan is essential for obtaining authorization to proceed.

Variation 3. Which TWO of the following are outputs of the Initiating a Project process?

medium
  • A.Project Plan
  • B.Project Initiation Documentation
  • C.Risk Register
  • D.Project Brief
  • E.Business Case

Why B: The correct outputs of the Initiating a Project process are the Project Initiation Documentation (PID) and the Business Case. The PID is a comprehensive document that consolidates key information, while the Business Case is refined and approved during this process. Option A (Project Plan) is an output of the Planning process, not Initiating a Project. Option C (Risk Register) is created during Initiating a Project but is part of the PID, not listed as a separate key output. Option D (Project Brief) is an output of the Starting Up a Project process. Therefore, only B and E are correct.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.