Which register records details of all quality activities planned and performed?

⚠ Common exam trap

The trap is confusing the Quality Register with other registers like the Issue or Risk Register; the key is that it specifically records quality activities.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Quality Register

The Quality Register records details of all quality activities planned and performed. In PRINCE2, it is a central log for quality management, capturing planned quality activities, results, and approvals.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Quality Register

    Why this is correct

    The Quality Register is the PRINCE2 record where all quality activities — planned and performed — are logged, including results of quality control and quality assurance reviews. It directly satisfies the stem's requirement to record details of every quality activity.

  • ✗

    Configuration Item Record

    Why it's wrong here

    The Configuration Item Record holds status, version and relationships for each configuration item under change control. It would be correct when tracking a product's configuration details, but it does not record planned or performed quality activities, which the Quality Register captures.

  • ✗

    Issue Register

    Why it's wrong here

    The Issue Register logs issues and concerns raised during the project, not planned or performed quality activities. It would be the right register when tracking a problem, change or off-specification needing management action, but the Quality Register is the one recording quality activities.

  • ✗

    Risk Register

    Why it's wrong here

    The Risk Register records identified risks, their probability, impact and responses, not quality activities. It would be the correct register when logging and managing uncertainty threatening project objectives, but quality activities planned and performed belong in the Quality Register.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In PRINCE2, which document is used to record quality activities and their results?

medium
  • A.Project Plan
  • ✓ B.Quality Register
  • C.Quality Management Strategy
  • D.Product Description

Why B: In PRINCE2, the Quality Register is the document used to record quality activities, including quality inspections, tests, and their results. It provides a log of all quality-related actions planned and completed throughout the project, and it is maintained by the Project Manager. The Quality Register is distinct from the Quality Management Strategy, which defines the approach, and the Product Description, which defines quality criteria for a product.

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.