Courseiva
PRINCE2 Processes →easyMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

Which process covers the Project Board's decision to authorise project closure?

⚠ Common exam trap

PRINCE2F often tests the confusion between the Project Manager's role in Closing a Project (executing closure) and the Project Board's role in Directing a Project (authorising closure). Candidates frequently pick 'Closing a Project' because it sounds like the process that covers closure, but the question specifically asks for the Board's decision.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Directing a Project

The Directing a Project process is the responsibility of the Project Board and includes the activity 'Authorise Project Closure'. This activity is where the Project Board reviews the End Project Report and gives approval to close the project. It is a decision-making process, not a delivery or management process, and it sits above the other processes in the PRINCE2 process model.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary prepares the End Stage Report and next Stage Plan for the Project Board's authorisation of the following stage, not project closure. It is tempting because it also produces a Board decision. Closure authorisation belongs to Closing a Project, triggered after the final stage's products are accepted.

  • ✗

    Initiating a Project

    Why it's wrong here

    Initiating a Project assembles the Project Initiation Documentation and business case, ending with the Project Board's authorisation to proceed, not to close. It is tempting because both processes involve a Project Board decision point. Closure authorisation instead sits in Closing a Project, after the final stage boundary.

  • ✓

    Directing a Project

    Why this is correct

    Directing a Project is the board-level process covering authorisation decisions, including authorising project closure via the End Project activity. It sits above Managing a Stage Boundary, which merely prepares the closure information the board then approves.

  • ✗

    Closing a Project

    Why it's wrong here

    Closing a Project handles closure activities after the Project Board has already authorised closure; the authorisation decision itself sits in Directing a Project. It tempts because closure preparation and lessons reporting occur within that process.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.