Courseiva
PRINCE2 ProcesseseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which process covers the Project Board's decision to authorise project closure?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

The Project Board uses the Directing a Project process to authorise closure, based on the recommendation from CP.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Managing a Stage Boundary

    Why it's wrong here

    SB ends stages, not the project.

  • Initiating a Project

    Why it's wrong here

    IP initiates the project, not closes it.

  • Directing a Project

    Why this is correct

    DP includes the activity 'Authorise Project Closure'.

  • Closing a Project

    Why it's wrong here

    CP prepares the closure recommendation; the Board authorises it in DP.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.