PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Which PRINCE2 principle is being applied when the Project Manager escalates an issue that is outside the stage tolerance?

⚠ Common exam trap

Many candidates confuse the stage-based planning and control ('Manage by stages') with the escalation of out-of-tolerance issues ('Manage by exception'), which is a specific control mechanism for handling deviations beyond delegated authority.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Manage by exception

The principle of 'Manage by exception' is applied when the Project Manager escalates an issue that exceeds the stage tolerance. This principle establishes that each management level (e.g., Project Manager, Project Board) has defined tolerances (e.g., time, cost, quality) for their delegated authority; if a forecast or actual deviation goes beyond those tolerances, the issue must be escalated to the next management level for a decision. By escalating the out-of-tolerance issue, the Project Manager is following the exception-based control mechanism that is core to PRINCE2.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Manage by stages

    Why it's wrong here

    Manage by stages concerns dividing the project into controllable chunks with delegated tolerances and stage boundaries, not escalation itself. Escalating a breach of stage tolerance to the board demonstrates the 'manage by exception' principle, which sets defined tolerances and escalates only when they are exceeded.

  • ✓

    Manage by exception

    Why this is correct

    Manage by exception gives the Project Manager authority to run the stage within agreed tolerances and mandates escalation only when a forecast breach exceeds them. Escalating the out-of-tolerance issue to the project board is precisely the defined exception trigger.

  • ✗

    Tailor to suit the project environment

    Why it's wrong here

    Tailoring concerns adapting PRINCE2 to the project's scale, environment and complexity. Escalating an issue beyond stage tolerance is governed by pre-agreed tolerance levels and the 'manage by exception' principle, which defines what authority the Project Manager holds before escalation to the board.

  • ✗

    Continued business justification

    Why it's wrong here

    Continued business justification concerns whether the project remains viable and aligned to a valid Business Case throughout. Escalating a tolerance breach is about defined authority limits and exception reporting, which is the 'manage by exception' principle, not ongoing justification of the project's value.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.