PRINCE2F PRINCE2 Practices Practice Question
Which PRINCE2 practice describes the management of product versions and baselines?
⚠ Common exam trap
Candidates often confuse the Change practice with Quality, thinking that version control is part of quality management, but PRINCE2 explicitly assigns version and baseline management to the Change practice, not Quality.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Change
B is correct because the Change practice in PRINCE2 is responsible for managing product versions and baselines. It ensures that all changes to products are controlled, recorded, and traceable, using configuration management to track versions and baselines of products throughout the project lifecycle.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Progress
Why it's wrong here
Progress focuses on monitoring and tolerances.
- ✓
Change
Why this is correct
Correct. Configuration management is part of the Change practice.
- ✗
Risk
Why it's wrong here
Risk deals with uncertainties.
- ✗
Quality
Why it's wrong here
Quality focuses on quality criteria and checking, not version control.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.