Which of the following is a difference between the Directing a Project and Controlling a Stage processes?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Directing a Project is performed by the Project Board; Controlling a Stage is performed by the Project Manager

Directing a Project is performed by the Project Board; Controlling a Stage is performed by the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Directing a Project is performed by the Project Manager; Controlling a Stage is performed by the Team Manager

    Why it's wrong here

    The roles are reversed: Directing a Project is performed by the Project Board, while Controlling a Stage is performed by the Project Manager. It is tempting because both processes involve management activity at different levels, but the stem asks for a genuine difference, and this option misassigns both roles.

  • ✓

    Directing a Project is performed by the Project Board; Controlling a Stage is performed by the Project Manager

    Why this is correct

    Directing a Project sits with the Project Board, providing overall direction and decision authority, while Controlling a Stage is delegated to the Project Manager for day-to-day stage delivery. This accountability split satisfies the stem's required difference.

  • ✗

    Both are performed by the Project Board

    Why it's wrong here

    Only Directing a Project is performed by the Project Board; Controlling a Stage is performed by the Project Manager. It is tempting because the Project Board does direct throughout the project, but claiming both processes share the same performer contradicts the distinct accountability split that defines their difference.

  • ✗

    Directing a Project is performed once; Controlling a Stage is performed multiple times

    Why it's wrong here

    Directing a Project runs continuously from project start to closure, not once; it is Controlling a Stage that repeats per stage. It is tempting because stage boundaries give Controlling a Stage a clear repeat cycle, but Directing a Project is ongoing decision-making, so the frequency contrast is stated incorrectly.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.