Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which document is the key output of the Initiating a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Initiation Documentation

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, providing the foundation for the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Brief

    Why it's wrong here

    The Project Brief is an output of Starting Up a Project.

  • Business Case

    Why it's wrong here

    The Business Case is developed in Starting Up a Project and refined during Initiating a Project, but the PID is the main deliverable.

  • Project Initiation Documentation

    Why this is correct

    The PID is the key output of Initiating a Project.

  • Project Plan

    Why it's wrong here

    The Project Plan is a component of the PID but not the key output alone.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.