What is the first step in the PRINCE2 recommended risk management procedure?

⚠ Common exam trap

Many candidates confuse the order of the risk management steps, particularly placing 'Assess' before 'Identify' due to a common misconception that assessment comes first in risk management processes.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Identify

The PRINCE2 risk management procedure follows a logical sequence: Identify, Assess, Plan, Implement, and Communicate. The first step is 'Identify' because risks must be identified before they can be assessed or managed. Without identification, no further risk management actions are possible.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Plan

    Why it's wrong here

    Plan follows Identify in PRINCE2's risk management procedure, so it cannot be first. It is tempting because planning is a genuine step within that procedure, and would be correct if the question asked which step immediately follows identifying risks and their context.

  • ✗

    Assess

    Why it's wrong here

    Assess comes after Identify, covering estimation and evaluation of each risk. It is tempting because assessment is a real, substantial stage of PRINCE2 risk management, and would be correct if the question asked what follows identifying risks rather than what begins the procedure.

  • ✗

    Implement

    Why it's wrong here

    Implementation follows identification, assessment and planning in PRINCE2's risk procedure, so it cannot be first. It is tempting because implementing responses is the visible payoff of risk work, and would be the right focus once a response has been planned and approved for execution.

  • ✓

    Identify

    Why this is correct

    Identify is the first step of PRINCE2's risk management procedure, preceding Assess, Plan and Implement. Context is established and risks are captured in the Risk Register before any evaluation occurs, satisfying the stem's requirement for the initial step.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. What is the first step in the recommended risk management procedure?

medium
  • A.Implement
  • B.Assess
  • C.Plan
  • ✓ D.Identify

Why D: The risk management procedure steps are: Identify, Assess, Plan, Implement, Communicate. Identify is first.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.