Courseiva
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

What is the difference between a Request for Change and an Off-specification?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

A Request for Change proposes a modification to a product specification, while an Off-specification is a product that has not met its specification

Ly captures the difference: a Request for Change (RFC) is a proposal to modify a product specification, often due to a new requirement, while an Off-specification is a product that has failed to meet its agreed specification. Both are types of issues in PRINCE2. Options A, B, and C are incorrect: A misattributes who raises them, B incorrectly relates to product timeframes, and C wrongly associates RFCs with scope and Off-specifications with schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • A Request for Change is raised by the Project Manager, while an Off-specification is raised by the Team Manager

    Why it's wrong here

    Who raises it does not define the difference; both can be raised by anyone.

  • A Request for Change is for future products, while an Off-specification is for completed products

    Why it's wrong here

    Both can apply to any product at any stage.

  • A Request for Change is about scope changes, while an Off-specification is about schedule changes

    Why it's wrong here

    Off-specifications are about products not meeting specification, not schedule.

  • A Request for Change proposes a modification to a product specification, while an Off-specification is a product that has not met its specification

    Why this is correct

    This is the key distinction: RFC is a proposed change; Off-spec is a failure to meet the agreed specification.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.