PRINCE2F Practice Question: Overview of PRINCE2 and the project environment
What is the difference between a Request for Change and an Off-specification?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
A Request for Change proposes a modification; an Off-specification identifies a gap in requirements
A Request for Change is a proposed modification, while an Off-specification is something that was required but not delivered.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
An Off-specification is always raised by the Project Manager
Why it's wrong here
It can be raised by anyone.
- ✗
A Request for Change is always urgent; an Off-specification is not
Why it's wrong here
Urgency is not the defining difference.
- ✗
There is no difference
Why it's wrong here
They are different types of issues.
- ✓
A Request for Change proposes a modification; an Off-specification identifies a gap in requirements
Why this is correct
Correct: RC is a change; Off-spec is a failure to meet a requirement.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.