What is the difference between a Request for Change and an Off-specification?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

A Request for Change proposes a modification; an Off-specification identifies a gap in requirements

A Request for Change is a proposed modification, while an Off-specification is something that was required but not delivered.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    An Off-specification is always raised by the Project Manager

    Why it's wrong here

    An Off-specification may be raised by anyone, including team members or suppliers, not solely the Project Manager. It is tempting because the Project Manager often escalates them, but the defining difference from a Request for Change is that an Off-specification covers something the project should deliver but currently cannot.

  • ✗

    A Request for Change is always urgent; an Off-specification is not

    Why it's wrong here

    Urgency is not a defining criterion; both are handled through the same change control approach, and either can be urgent. It is tempting because changes are often perceived as time-critical, but the real distinction is that a Request for Change proposes altering baselined products, whereas an Off-specification flags a failure to meet an agreed requirement.

  • ✗

    There is no difference

    Why it's wrong here

    A Request for Change proposes an alteration to baselined products or scope, whereas an Off-specification reports that agreed tolerances have already been breached. Claiming no difference ignores that one is proactive and the other reactive. It tempts candidates who see both as change-related paperwork, yet they are distinct PRINCE2 issue types requiring different handling.

  • ✓

    A Request for Change proposes a modification; an Off-specification identifies a gap in requirements

    Why this is correct

    An RFC proposes modifying a baselined product, whereas an Off-specification records where a product fails to meet its agreed requirements. This separates proposed change from identified non-conformance, satisfying the stem's requirement to distinguish the two PRINCE2 change control types.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.