Question 26 of 1,731
PRINCE2 PracticesmediumMultiple SelectObjective-mapped

Quick Answer

The answer is the Executive and the Senior User. These two roles, along with the Senior Supplier, form the mandatory Project Board in PRINCE2, which acts as the project’s decision-making body. The Executive owns the business case and holds ultimate authority, while the Senior User represents the end users and ensures the project delivers the expected benefits. On the PRINCE2 Foundation exam, this concept tests your understanding of governance structure, often appearing in questions that ask you to identify which roles are accountable for key decisions versus those that are advisory. A common trap is confusing the Project Manager or Project Assurance with board members, but remember that the board is strictly the Executive, Senior User, and Senior Supplier. To lock this in, use the mnemonic “Eat, Sleep, Use” for Executive, Senior Supplier, and Senior User—the three seats at the board table.

PRINCE2F PRINCE2 Practices Practice Question

This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO roles are part of the Project Board?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior User

The Project Board is the decision-making body of a PRINCE2 project, and its mandatory roles are the Executive, Senior User, and Senior Supplier. The Senior User (Option C) is correct because they represent the interests of those who will use the project's outputs and are responsible for specifying requirements and ensuring the project delivers the expected benefits. The Executive (Option D) is correct as they own the business case and have ultimate authority over the project.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Team Manager

    Why it's wrong here

    Team Managers are not on the Project Board.

  • Project Manager

    Why it's wrong here

    The Project Manager reports to the Board but is not a member.

  • Senior User

    Why this is correct

    The Senior User is a member of the Project Board.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Executive

    Why this is correct

    The Executive is a member of the Project Board.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Project Support

    Why it's wrong here

    Project Support is not on the Project Board.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PeopleCert often tests the distinction between management roles (Project Board) and delivery/administrative roles (Team Manager, Project Support), leading candidates to mistakenly include the Project Manager as a Board member because they are the most visible role in project execution.

Detailed technical explanation

How to think about this question

Under PRINCE2, the Project Board is responsible for key decisions such as approving stage plans, reviewing the business case, and authorizing project closure. The Executive chairs the Board and is accountable for the project's success, while the Senior User ensures the final product meets user needs and that benefits are realized. In a real-world scenario, if a project fails to deliver expected benefits, the Senior User is held accountable for not clearly defining requirements or accepting outputs that do not meet user needs.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Senior User — The Project Board is the decision-making body of a PRINCE2 project, and its mandatory roles are the Executive, Senior User, and Senior Supplier. The Senior User (Option C) is correct because they represent the interests of those who will use the project's outputs and are responsible for specifying requirements and ensuring the project delivers the expected benefits. The Executive (Option D) is correct as they own the business case and have ultimate authority over the project.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

6 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which THREE of the following are roles on the Project Board?

medium
  • A.Senior Supplier
  • B.Project Support
  • C.Senior User
  • D.Executive
  • E.Project Manager

Why A: The Project Board consists of Executive, Senior User, and Senior Supplier.

Variation 2. Which TWO of the following are typical roles in the Project Board?

medium
  • A.Senior Supplier
  • B.Project Manager
  • C.Team Manager
  • D.Project Support
  • E.Executive

Why A: The Project Board consists of the Executive, Senior User, and Senior Supplier. Senior Supplier is part of the Board; Project Manager is not on the Board.

Variation 3. Which TWO roles are permanent members of the Project Board?

easy
  • A.Executive
  • B.Team Manager
  • C.Senior User
  • D.Project Manager
  • E.Project Support

Why A: The Project Board consists of the Executive, Senior User, and Senior Supplier. The Project Manager is not a permanent member.

Variation 4. Which TWO roles are members of the Project Board?

medium
  • A.Executive
  • B.Project Manager
  • C.Senior Supplier
  • D.Team Manager
  • E.Project Support

Why A: The Project Board consists of the Executive, Senior User, and Senior Supplier. The Project Manager and Team Manager are not board members.

Variation 5. Which TWO are roles that are part of the Project Board?

easy
  • A.Project Manager
  • B.Project Assurance
  • C.Team Manager
  • D.Senior User
  • E.Executive (Senior Responsible Owner)

Why D: The Project Board consists of Executive (Senior Responsible Owner), Senior User, and Senior Supplier.

Variation 6. Which TWO roles are part of the Project Board?

medium
  • A.Senior User
  • B.Executive
  • C.Project Manager
  • D.Team Manager
  • E.Change Authority

Why A: The Project Board consists of the Executive, Senior User, and Senior Supplier. Therefore, options A and B are correct. Option C is wrong because the Project Manager is not on the Board. Option D is wrong because Change Authority is a separate role. Option E is wrong because the Team Manager reports to the Project Manager.

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.