In which process is the Project Manager appointed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Starting Up a Project

The Project Manager is appointed during the Starting Up a Project process, as part of preparing for initiation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Starting Up a Project

    Why this is correct

    SU includes selecting the Project Manager and assigning them to the project.

  • Directing a Project

    Why it's wrong here

    DP is the Project Board process; the Board may appoint the PM but the appointment is done in SU.

  • Initiating a Project

    Why it's wrong here

    IP assumes the PM is already appointed and is managing the initiation stage.

  • Controlling a Stage

    Why it's wrong here

    CS occurs after the PM is appointed.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.