PRINCE2F PRINCE2 Processes Practice Question
In which process is the Project Manager appointed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Starting Up a Project
The Project Manager is appointed during the Starting Up a Project process, as part of preparing for initiation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Starting Up a Project
Why this is correct
SU includes selecting the Project Manager and assigning them to the project.
- ✗
Directing a Project
Why it's wrong here
DP is the Project Board process; the Board may appoint the PM but the appointment is done in SU.
- ✗
Initiating a Project
Why it's wrong here
IP assumes the PM is already appointed and is managing the initiation stage.
- ✗
Controlling a Stage
Why it's wrong here
CS occurs after the PM is appointed.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.