In the context of PRINCE2 configuration management, what is the purpose of a 'baseline'?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To provide a basis for change control by capturing the agreed state of a product

A baseline is a snapshot of a configuration item's state at a specific point in time. It is used to provide a fixed reference for control and management, ensuring changes are made in a controlled manner.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To define the quality criteria for a product

    Why it's wrong here

    Quality criteria are defined in the Product Description, not in a baseline.

  • To schedule the delivery of products

    Why it's wrong here

    Scheduling is part of planning, not configuration management baselines.

  • To provide a basis for change control by capturing the agreed state of a product

    Why this is correct

    Correct. A baseline is the agreed reference point against which changes are assessed.

  • To record the current version of a product

    Why it's wrong here

    Version control tracks versions, but a baseline is specifically a snapshot for control purposes.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which PRINCE2 practice describes the management of product versions and baselines?

easy
  • A.Progress
  • B.Change
  • C.Risk
  • D.Quality

Why B: B is correct because the Change practice in PRINCE2 is responsible for managing product versions and baselines. It ensures that all changes to products are controlled, recorded, and traceable, using configuration management to track versions and baselines of products throughout the project lifecycle.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.