In PRINCE2, who is responsible for ensuring that the project remains viable and for approving major changes to the project's scope?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

The Executive (Senior Responsible Owner) is accountable for the project's business justification and for approving major changes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Executive

    Why this is correct

    The Executive owns the Business Case and is accountable to the Project Board for the project's ongoing viability, including approving major scope changes. This single-point accountability for continued business justification is exactly the responsibility the stem describes.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents supplier interests and provides supplier resources and expertise, but does not own the business case. The Project Board as a whole ensures viability, with the Executive accountable for the business case and major scope decisions. It is tempting because suppliers influence feasibility, yet viability and scope approval sit with the Executive.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager runs the project day to day and prepares the business case, but accountability for viability and major scope changes rests with the Project Board, specifically the Executive. It is tempting because the Project Manager escalates and recommends, yet approval authority is not delegated to that role.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User specifies requirements and represents user interests, ensuring the solution meets user needs, but does not own the business case. The Executive ensures viability and approves major scope changes. It is tempting because users drive scope, yet the business justification and approval authority sit with the Executive.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.