Overview of PRINCE2 and the project environmentmediumMultiple ChoiceObjective-mapped

PRINCE2F Practice Question: Overview of PRINCE2 and the project environment

In PRINCE2, what is the purpose of the Risk theme?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To identify, assess, and control uncertainties

The Risk theme aims to identify, assess, and control uncertainties that could affect the project. Option D is correct. Option A describes the Progress theme. Option B describes the Business Case theme. Option C describes the Change theme.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To monitor the progress of the project

    Why it's wrong here

    That is the Progress theme.

  • To establish the viability of the project

    Why it's wrong here

    That is the Business Case theme.

  • To manage issues and changes

    Why it's wrong here

    That is the Change theme.

  • To identify, assess, and control uncertainties

    Why this is correct

    This is the purpose of the Risk theme.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.