In PRINCE2, what is the purpose of the Risk theme?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

To identify, assess, and control uncertainties

The Risk theme aims to identify, assess, and control uncertainties that could affect the project. Option D is correct. Option A describes the Progress theme. Option B describes the Business Case theme. Option C describes the Change theme.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    To monitor the progress of the project

    Why it's wrong here

    Progress monitoring belongs to the Progress theme, which compares actuals against the plan and business case. Risk is tempting because its register is reviewed at stage boundaries, but the theme's purpose is identifying, assessing and controlling uncertainty, not tracking schedule or cost performance.

  • ✗

    To establish the viability of the project

    Why it's wrong here

    Viability is established by the Business Case theme, which justifies the investment and confirms continued desirability. Risk is tempting because threats can undermine the business case, yet the theme's purpose is the systematic identification, assessment and control of uncertainty, not validating whether the project should proceed.

  • ✗

    To manage issues and changes

    Why it's wrong here

    Issues and changes are handled by the Change theme, which covers issue capture, configuration management and change control. Risk is tempting because both themes address uncertainty, but the Risk theme's purpose is managing potential future threats and opportunities, not resolving problems that have already occurred.

  • ✓

    To identify, assess, and control uncertainties

    Why this is correct

    The Risk theme covers identifying, assessing and controlling uncertainty, giving the project a structured approach to managing threats and opportunities. This satisfies the stem by naming all three activities, unlike themes addressing business justification, organisation or quality.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.