PRINCE2F People: organizations, teams, and leadership Practice Question

In a PRINCE2 project, the Project Board has decided to delegate some of its change control decisions to a Change Authority. The Project Manager needs to ensure that the Change Authority has the necessary information to make decisions. Which role is responsible for providing the Change Authority with the details of a Request for Change?

⚠ Common exam trap

Test-takers frequently confuse Project Support's administrative role with the Project Manager's responsibility for assessing and presenting change details to the Change Authority.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Manager

The Project Manager assesses each Request for Change, evaluates its impact on the project's baselines, and provides the necessary information to the Change Authority for a decision. This ensures that the Change Authority can make an informed choice. The Project Manager is accountable for the change control procedure and acts as the link between those raising changes and those deciding on them.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User is a member of the Project Board and may be involved in change decisions if they are escalated. However, the Senior User does not provide the detailed assessment of a Request for Change to the Change Authority. That is an operational task performed by the Project Manager, who ensures the Change Authority has the necessary information.

  • ✗

    Team Manager

    Why it's wrong here

    The Team Manager is responsible for delivering the products within a Work Package and may raise issues or changes. However, the Team Manager does not assess and present the details of a Request for Change to the Change Authority. This is a Project Manager responsibility, as the Project Manager owns the change control process.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative support, such as maintaining the change log and distributing information. However, it is the Project Manager's responsibility to assess and present the details of a Request for Change to the Change Authority. Project Support does not make decisions or provide the analysis required for change control.

  • ✓

    Project Manager

    Why this is correct

    The Project Manager is responsible for assessing the impact of a Request for Change and presenting the details to the Change Authority for a decision. This includes evaluating the change against the project's baselines and providing a recommendation. The Project Manager acts as the conduit between the change initiator and the decision-maker.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.