Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During the Managing Product Delivery process, a Team Manager discovers that a product cannot meet its quality criteria without significant extra work. What should the Team Manager do?

⚠ Common exam trap

A common mix-up: candidates think the Team Manager should directly inform the Project Board (Option D) because quality is a board-level concern, but PRINCE2 strictly requires escalation through the Project Manager first.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an issue to the Project Manager for direction

In PRINCE2, the Team Manager works within the constraints set by the Project Manager. When a product cannot meet its quality criteria without significant extra work, the Team Manager must escalate this as an issue to the Project Manager, who has the authority to decide on changes to scope, quality, or budget. This aligns with the 'Manage by Exception' principle and the defined roles in the Managing Product Delivery process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Modify the quality criteria to match what can be achieved

    Why it's wrong here

    Quality criteria are defined in the Product Description and cannot be changed unilaterally.

  • Raise an issue to the Project Manager for direction

    Why this is correct

    The Team Manager should raise an issue to the PM, who will decide on corrective action or change.

  • Proceed with the work and report the variance in the next Checkpoint Report

    Why it's wrong here

    Significant issues should be escalated immediately, not delayed.

  • Inform the Project Board directly

    Why it's wrong here

    The Team Manager communicates via the PM, not directly to the Project Board.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.