During the Managing a Stage Boundary process, the Project Manager is preparing the End Stage Report. The Project Board has asked for an update on how the project is performing against the business case. The Project Manager knows that the Senior User has been closely involved in benefits reviews. Which role is accountable for confirming that the project's products will deliver the expected benefits?

⚠ Common exam trap

The trap here is attributing benefits confirmation to the Executive, who holds overall business case accountability, rather than to the Senior User, who is specifically accountable for benefits realization from the user perspective.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Senior User

The Senior User is accountable for ensuring that the project's products will deliver the expected benefits. This role represents the user community and is responsible for specifying their needs, confirming that the solution meets those needs, and realizing the benefits. While the Executive is ultimately accountable for the business case, the Senior User provides the user perspective and confirms benefits realization.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Executive

    Why it's wrong here

    The Executive is ultimately accountable for the business case and ensuring that the project delivers the expected benefits. However, the day-to-day confirmation that products will meet user needs and deliver benefits is delegated to the Senior User. The Executive retains overall accountability but does not typically confirm individual product benefits.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager is responsible for the day-to-day management of the project and for delivering the products to the required quality, cost, and time. However, the Project Manager does not confirm that the products will deliver the expected benefits. That accountability lies with the Senior User, who represents the users and ensures the products meet their needs.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents the interests of those designing, developing, facilitating, procuring, and implementing the project's products. This role is accountable for the technical integrity of the project and ensuring that the supplier resources are available. The Senior Supplier does not confirm benefits realization, as that is the user's perspective.

  • ✓

    Senior User

    Why this is correct

    The Senior User is accountable for specifying the needs of those who will use the project's products and for ensuring that the solution will deliver the expected benefits. This includes confirming that the products meet user requirements and will realize the benefits defined in the business case. The Senior User represents the user community and is responsible for benefits realization.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.