Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

During the Controlling a Stage process, the Project Manager receives a Checkpoint Report from a Team Manager indicating a delay in delivering a Work Package. What should the Project Manager do first?

⚠ Common exam trap

The trap here is that candidates often jump to escalation (Option C) without recognizing that the Project Manager must first assess the impact and attempt corrective action within tolerances, as per the management by exception principle.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Assess the impact on the Stage Plan and decide on corrective action within stage tolerances

The Project Manager must first assess the impact of the delay on the Stage Plan and decide on corrective action within the agreed stage tolerances. This aligns with the PRINCE2 principle of management by exception, where the Project Manager handles deviations within tolerances before escalating. Only if the delay exceeds stage tolerances should an Exception Report be raised to the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Instruct the Team Manager to recover the delay within the Work Package tolerances

    Why it's wrong here

    The Team Manager should already be managing within tolerances. The PM may need to assess options first.

  • Close the Work Package and re-plan the stage

    Why it's wrong here

    Closing the Work Package would be premature; corrective action should be attempted first.

  • Raise an Exception Report to the Project Board immediately

    Why it's wrong here

    An Exception Report is only needed if stage tolerances are forecast to be exceeded. A delay may not require immediate escalation.

  • Assess the impact on the Stage Plan and decide on corrective action within stage tolerances

    Why this is correct

    The PM should first assess the impact and take action within delegated tolerances before escalating.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project is in its Controlling a Stage process. The Team Manager reports that a Work Package is likely to be completed late. The Project Manager reviews the Stage Plan and sees that stage tolerance is not forecast to be exceeded. What should the Project Manager do?

hard
  • A.Instruct the Team Manager to continue as planned.
  • B.Close the stage early.
  • C.Take corrective action within the tolerances delegated by the Project Board.
  • D.Escalate to the Project Board via an Exception Report.

Why C: Since stage tolerance is not threatened, the Project Manager can take corrective action within the delegated tolerances, such as re-planning or re-assigning resources, without escalating to the Project Board.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.