- A
Highlight Report
Why wrong: Highlight Reports are from PM to Project Board.
- B
Checkpoint Report
Correct. Checkpoint Reports are from Team Manager to Project Manager.
- C
End Stage Report
Why wrong: End Stage Reports are produced at stage end.
- D
Exception Report
Why wrong: Exception Reports are used for tolerance breaches.
Quick Answer
The answer is the Checkpoint Report. In PRINCE2, the Team Manager uses the Checkpoint Report to provide the Project Manager with a periodic progress update on a specific work package during a stage, typically on a weekly basis. This report is the formal, documented mechanism for the Team Manager to communicate completed work, next steps, and any issues or risks, ensuring the Project Manager can monitor progress against the stage plan. On the PRINCE2 Foundation exam, this question tests your understanding of the management products and their specific sender-receiver relationships; a common trap is confusing the Checkpoint Report with the Highlight Report, but remember that the Team Manager sends the Checkpoint Report to the Project Manager, while the Project Manager sends the Highlight Report to the Project Board. A simple memory tip: think of the Team Manager “checking in” with the Project Manager—hence, a Checkpoint Report.
PRINCE2F PRINCE2 Practices Practice Question
This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During a stage, the Team Manager reports progress to the Project Manager. Which report should the Team Manager use?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Checkpoint Report
In PRINCE2, the Team Manager reports progress to the Project Manager using the Checkpoint Report. This report is a periodic (typically weekly) progress update from the Team Manager to the Project Manager, covering work completed, next steps, and any issues within the work package. It is the formal mechanism for the Team Manager to report on progress during a stage.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Highlight Report
Why it's wrong here
Highlight Reports are from PM to Project Board.
- ✓
Checkpoint Report
Why this is correct
Correct. Checkpoint Reports are from Team Manager to Project Manager.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
End Stage Report
Why it's wrong here
End Stage Reports are produced at stage end.
- ✗
Exception Report
Why it's wrong here
Exception Reports are used for tolerance breaches.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is confusing the direction of reporting: candidates often pick Highlight Report because it sounds like a progress report, but it is produced by the Project Manager for the Project Board, not by the Team Manager for the Project Manager.
Detailed technical explanation
How to think about this question
The Checkpoint Report is defined in the PRINCE2 manual as a progress report from the Team Manager to the Project Manager, typically on a weekly basis. It includes actual progress against the plan, quality activities completed, and any issues or risks. This report is a key input to the Project Manager's Highlight Report, ensuring the Project Board receives consolidated progress information. The frequency of Checkpoint Reports is determined by the Project Manager and documented in the Work Package.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Practices — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Practices practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Checkpoint Report — In PRINCE2, the Team Manager reports progress to the Project Manager using the Checkpoint Report. This report is a periodic (typically weekly) progress update from the Team Manager to the Project Manager, covering work completed, next steps, and any issues within the work package. It is the formal mechanism for the Team Manager to report on progress during a stage.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.