PRINCE2 Practices →hardMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

During a stage, a Team Manager reports that a work package is likely to be delayed. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Assess the impact on stage tolerances and take corrective action if within tolerance

The Project Manager must assess the impact on stage tolerances. If the delay is within tolerance, they can take corrective action. If it exceeds tolerance, they must escalate via an Exception Report.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Close the work package and reassign the work to another team

    Why it's wrong here

    Closing the work package and reassigning work is a drastic response that discards the Team Manager's specialist knowledge and may breach the agreed Work Package tolerances. Reassignment suits a team genuinely unable to deliver; a forecast delay instead calls for corrective action within the Project Manager's delegated authority.

  • ✓

    Assess the impact on stage tolerances and take corrective action if within tolerance

    Why this is correct

    Stage tolerances define the delegated authority boundary. Assessing the delay's impact against them determines whether the Project Manager can act within the stage boundary or must escalate to the Project Board, since only the Board can approve exceeding stage tolerances.

  • ✗

    Immediately raise an Exception Report to the Project Board

    Why it's wrong here

    A likely delay is first assessed against the stage tolerances; only if the forecast breaches those tolerances does an Exception Report go to the Project Board. Raising one immediately bypasses the Project Manager's own tolerance analysis and escalation triggers defined in the Business Case.

  • ✗

    Instruct the Team Manager to continue as planned and report progress in the next Checkpoint Report

    Why it's wrong here

    Ignoring the forecast delay removes any corrective action before the stage boundary, so tolerance breach is discovered late. Continuing as planned suits minor variances within tolerance; here the Project Manager must first evaluate impact and take corrective action, escalating only if stage tolerances are threatened.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.