PRINCE2F PRINCE2 Practices Practice Question
During a stage, a team manager reports that a key product will be delivered two weeks late due to resource constraints. The project manager updates the stage plan and finds that the stage tolerance for time is about to be exceeded. What is the first action the project manager should take?
⚠ Common exam trap
Many exam-takers think the project manager can handle the delay internally by reassigning resources or revising plans, but PRINCE2 strictly requires escalation via an Exception Report when stage tolerance is forecast to be exceeded.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Issue an exception report to the project board
The project manager must escalate the issue to the project board because the stage tolerance for time is about to be exceeded. According to PRINCE2, when a forecast indicates that a stage will exceed its tolerances, the project manager must produce an Exception Report and submit it to the project board, which then decides on corrective action. This is a mandatory escalation step to maintain management by exception.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Issue an exception report to the project board
Why this is correct
When tolerance is forecast to be exceeded, the project manager must produce an Exception Report and seek guidance from the project board.
- ✗
Revise the project plan to absorb the delay
Why it's wrong here
The project manager cannot change the project plan without authorization; this exceeds their authority.
- ✗
Reassign resources to the delayed product
Why it's wrong here
This may help but the project manager must first inform the project board if tolerance is at risk.
- ✗
Request a concession from the project board
Why it's wrong here
Concessions are not a PRINCE2 term; the correct action is to escalate the deviation.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. During a stage, a Team Manager reports that a work package is likely to be delayed. What should the Project Manager do?
hard- A.Close the work package and reassign the work to another team
- ✓ B.Assess the impact on stage tolerances and take corrective action if within tolerance
- C.Immediately raise an Exception Report to the Project Board
- D.Instruct the Team Manager to continue as planned and report progress in the next Checkpoint Report
Why B: The Project Manager must assess the impact on stage tolerances. If the delay is within tolerance, they can take corrective action. If it exceeds tolerance, they must escalate via an Exception Report.
Variation 2. During a project, a Team Manager reports that a product will be delivered two weeks later than planned. The tolerance for the Work Package is one week. What should the Team Manager do?
hard- A.Update the Project Plan to reflect the delay
- B.Request a change to the Project Plan directly from the Project Board
- ✓ C.Issue an Exception Report to the Project Manager
- D.Continue with the work and inform the Project Manager in the next Checkpoint Report
Why C: When a Work Package tolerance is forecast to be exceeded, the Team Manager must escalate to the Project Manager via an Exception Report. The Project Manager can then negotiate corrective actions.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.