Courseiva
People: organizations, teams, and leadershiphardMultiple ChoiceObjective-mapped

Change Authority Delegation in PRINCE2

Which role can delegate change control decisions to a Change Authority?

Quick Answer

The answer is the Project Board. In PRINCE2, the Project Board holds ultimate authority over project governance, including change control, and it can formally delegate this responsibility to a Change Authority through the Project Initiation Documentation. This delegation allows the Change Authority to approve or reject change requests within predefined limits, such as cost or time thresholds, without requiring escalation for every decision. On the PRINCE2 Foundation exam, this concept tests your understanding of how authority flows from the strategic to the operational level, often appearing in questions about roles and responsibilities. A common trap is confusing the Change Authority with the Project Manager, who manages changes but does not have the delegated decision-making power. Remember the memory tip: the Board “boards” the big decisions, but can “authorize” a Change Authority to handle the smaller ones.

⚠ Common exam trap

Many candidates confuse the Project Board with its individual members (Executive or Senior User) and mistakenly think one person can delegate change authority, but PRINCE2 requires collective Board approval for such delegation.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board

In PRINCE2, the Project Board is responsible for overall project governance and can delegate its change control authority to a Change Authority. This delegation is formalized in the Project Initiation Documentation (PID) and allows the Change Authority to approve or reject change requests within predefined limits, such as cost or time thresholds, without needing to escalate every decision back to the Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The Project Manager does not have authority to delegate change control; this is a Project Board responsibility.

  • Project Board

    Why this is correct

    Correct: The Project Board can set up a Change Authority to approve changes within defined tolerances.

  • Executive

    Why it's wrong here

    The Executive alone cannot delegate; the Project Board must agree.

  • Senior User

    Why it's wrong here

    The Senior User is part of the Project Board but cannot delegate alone; the Board as a whole delegates.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

7 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. The Project Board has delegated change control decisions to a Change Authority. What is the key benefit of this delegation?

hard
  • A.It allows the Project Manager to approve all changes
  • B.It reduces the burden on the Project Board by handling smaller changes
  • C.It eliminates the need for the Configuration Management process
  • D.It ensures all changes are approved by the Senior Supplier

Why B: Delegating change control decisions to a Change Authority allows the Project Board to focus on strategic oversight and major decisions, while the Change Authority handles smaller, low-impact changes efficiently. This reduces the administrative burden on the Project Board and speeds up the change process, ensuring that minor changes do not require escalation to the board. In PRINCE2, this delegation is a key mechanism for balancing control with agility, as defined in the Change theme.

Variation 2. The Project Board has delegated authority for change control decisions to a separate body. What is this body called?

medium
  • A.Change Authority
  • B.Project Support
  • C.Project Assurance
  • D.Senior Supplier

Why A: In PRINCE2, the Change Authority is a body to which the Project Board delegates responsibility for making decisions on change requests and off-specifications, within defined limits. This allows the board to focus on strategic oversight while empowering a separate group to handle change control efficiently. The Change Authority is formally defined in the 'Organize' process and its authority is documented in the Project Initiation Documentation.

Variation 3. Which role delegates change control decisions to a Change Authority?

easy
  • A.Team Manager
  • B.Project Board
  • C.Senior Supplier
  • D.Project Manager

Why B: In PRINCE2, the Project Board is responsible for overall project governance, including delegating change control decisions to a Change Authority. This delegation allows the Change Authority to approve or reject change requests within predefined limits, freeing the Board from day-to-day change management while retaining strategic oversight.

Variation 4. Which TWO statements correctly describe the Change Authority role?

hard
  • A.It operates within limits set by the Project Board
  • B.It is responsible for all change decisions without limits
  • C.It is the same as Project Support
  • D.It is an optional role delegated by the Project Board
  • E.It is always performed by the Project Manager

Why A: The Change Authority role in PRINCE2 operates within limits set by the Project Board. These limits define the scope of authority for approving change requests, ensuring that the Change Authority can make decisions without escalating every change to the Project Board, as long as the change falls within the agreed tolerances.

Variation 5. What is the purpose of the Change Authority role in PRINCE2?

medium
  • A.To manage the project's risk register.
  • B.To authorize the project budget.
  • C.To audit the project's compliance with PRINCE2.
  • D.To make decisions on change requests within agreed limits.

Why D: The Change Authority is an optional role that is delegated by the Project Board to make decisions on change requests within defined limits, to streamline the change control process.

Variation 6. In PRINCE2, what is the role of the Change Authority?

medium
  • A.To manage the configuration of project products
  • B.To authorize Work Packages on behalf of the Project Manager
  • C.To make decisions on change requests within delegated authority
  • D.To approve all changes to the project scope

Why C: The Change Authority is a role defined in PRINCE2's Change Control approach, responsible for reviewing and making decisions on change requests within limits of delegated authority set by the Project Board. This ensures that minor changes can be approved quickly without escalating every request to the Project Board, balancing control with efficiency.

Variation 7. The Project Board is considering a Request for Change. Which role is authorized to approve changes within delegated limits?

medium
  • A.Project Manager
  • B.Senior Supplier
  • C.Senior User
  • D.Change Authority

Why D: The Change Authority role is specifically authorized to approve Requests for Change within delegated limits set by the Project Board. This delegation allows the Change Authority to make decisions on low-impact changes without requiring full Board approval, streamlining the change control process.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.