PRINCE2F People: organizations, teams, and leadership Practice Question

A Project Manager is setting up the project management team for a new project. The Project Board has been appointed, and the Project Manager is now defining the responsibilities of the Team Manager. Which TWO of the following are responsibilities of the Team Manager in PRINCE2? (Choose two.)

⚠ Common exam trap

The trap here is assuming that the Team Manager has broader project-level responsibilities such as approving the Business Case or authorizing stage boundaries, which are actually held by the Project Board.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Manage the team on a day-to-day basis

The Team Manager is responsible for managing the team on a day-to-day basis and ensuring that products are produced to the required quality criteria. These responsibilities are defined in the Work Package and are essential for the successful delivery of the project's products.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Manage the team on a day-to-day basis

    Why this is correct

    The Team Manager is responsible for the day-to-day management of the team, including assigning work, monitoring progress, and resolving issues. They ensure that the team remains focused on producing the products defined in the Work Package and report progress to the Project Manager.

  • ✓

    Ensure that the team produces products to the required quality criteria

    Why this is correct

    The Team Manager is responsible for managing the team to produce the required products according to the quality criteria defined in the Work Package. This includes ensuring that quality control activities are performed and that products meet the agreed standards before being handed over.

  • ✗

    Approve the project's Business Case

    Why it's wrong here

    The Business Case is approved by the Project Board, specifically the Executive, not by the Team Manager. The Team Manager's role is focused on the delivery of products within the constraints of the Work Package, and they do not have the authority to approve the Business Case.

  • ✗

    Appoint the Project Assurance role

    Why it's wrong here

    The Project Assurance role is appointed by the Project Board, not the Team Manager. Project Assurance provides independent oversight of the project on behalf of the Project Board, and the Team Manager has no role in appointing this position.

  • ✗

    Authorize the project's stage boundaries

    Why it's wrong here

    Authorizing stage boundaries is a responsibility of the Project Board, not the Team Manager. The Team Manager is involved in producing the products for a stage, but they do not have the authority to authorize the project to proceed to the next stage.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.