Question 1,719 of 1,731
Overview of PRINCE2 and the project environmentmediumMultiple ChoiceObjective-mapped

Quick Answer

The correct action when a PRINCE2 business case tolerance is breached is to recommend closure of the project because the business case is no longer viable. This is the right choice because PRINCE2 is built on the principle of continued business justification, meaning the project must remain worthwhile throughout its lifecycle. Here, the project has consumed 95% of the budget while delivering only 40% of the scope, which clearly exceeds the agreed cost tolerance of +/-10% and makes the original benefits unachievable. On the PRINCE2 Foundation exam, this scenario tests your understanding that exceeding tolerance does not automatically mean escalation for a fix—it signals that the business case itself is broken, and the project manager must advise the project board to close the project to prevent further waste. A common trap is thinking the board should simply re-plan or request more budget, but PRINCE2 demands closure when the costs outweigh the benefits. Remember the memory tip: “95% spent, 40% done—tolerance breached, business case gone.”

PRINCE2F Practice Question: Overview of PRINCE2 and the project environment

This PRINCE2F practice question tests your understanding of overview of prince2 and the project environment. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is reviewing a project that has been running for three months. The business case was approved with a cost tolerance of +/- 10%. The project has already spent 95% of the budget but has only completed 40% of the scope. The project board is meeting to decide the project's fate. The project manager should advise the board to:

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Recommend closure of the project because the business case is no longer viable

Option C is correct because the project has consumed 95% of the budget while delivering only 40% of the scope, making the original business case no longer viable. PRINCE2 requires continuous business justification; if the costs outweigh the benefits, the project should be closed. The project manager must advise the board to close the project as continuing would waste further resources.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request a budget increase and complete the project

    Why it's wrong here

    The budget overrun is too severe; a simple increase does not address the poor cost performance.

  • Continue as planned but monitor costs more tightly

    Why it's wrong here

    The project is not viable; continuing ignores the fundamental issue.

  • Recommend closure of the project because the business case is no longer viable

    Why this is correct

    PRINCE2 requires ongoing business case validation; if the project cannot deliver benefits within tolerance, closure is appropriate.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Proceed with an exception plan without board approval

    Why it's wrong here

    Exception plans require board approval; bypassing change control violates PRINCE2 principles.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PeopleCert often tests the misconception that a project can be saved by simply requesting more budget or monitoring costs, but PRINCE2 demands that the business case be re-evaluated when tolerance is breached, and if it is no longer viable, the project must be closed.

Detailed technical explanation

How to think about this question

Under PRINCE2, the business case is the key document for continued justification; if the projected costs exceed the agreed tolerance (here +/-10%), the project is in exception and must be escalated to the board. The board then decides whether to approve an exception plan (which includes revised costs and schedule) or close the project. In this scenario, the 55% gap between spend and completion indicates the original business case is fundamentally broken, making closure the only viable option.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

Overview of PRINCE2 and the project environment — This question tests Overview of PRINCE2 and the project environment — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Recommend closure of the project because the business case is no longer viable — Option C is correct because the project has consumed 95% of the budget while delivering only 40% of the scope, making the original business case no longer viable. PRINCE2 requires continuous business justification; if the costs outweigh the benefits, the project should be closed. The project manager must advise the board to close the project as continuing would waste further resources.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.