A Project Manager is leading a project using PRINCE2. The project is in the 'Controlling a Stage' process. A Work Package has been assigned to a Team Manager. Which document authorizes the Team Manager to start work on the Work Package?

⚠ Common exam trap

Test-takers frequently confuse the Stage Plan, which controls the stage, with the Work Package, which authorizes specific work.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Work Package

The Work Package is the authorization document given to the Team Manager to start work. It contains the necessary information and constraints, and its agreement signifies the Team Manager's commitment to deliver the specified products. The Stage Plan, Highlight Report, and Checkpoint Report serve different purposes and do not authorize work.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Work Package

    Why this is correct

    The Work Package is the document that authorizes the Team Manager to start work. It includes the product description, constraints, interfaces, and reporting requirements. Once agreed, it serves as the authority for the Team Manager to proceed with the assigned work.

  • ✗

    Checkpoint Report

    Why it's wrong here

    The Checkpoint Report is produced by the Team Manager to report progress to the Project Manager. It is a monitoring tool, not an authorization document. It does not grant permission to start work; it is used after work has begun.

  • ✗

    Stage Plan

    Why it's wrong here

    The Stage Plan is used by the Project Manager to control the stage, but it does not directly authorize a Team Manager to start work on a specific Work Package. It provides the overall stage context, but the Work Package is the specific authorization for the Team Manager.

  • ✗

    Highlight Report

    Why it's wrong here

    The Highlight Report is a progress report from the Project Manager to the Project Board. It does not authorize work; it informs stakeholders about stage progress. It is not used to assign or authorize Work Packages to Team Managers.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.