Courseiva

PRINCE2F Project Initiation and Stages Practice Question

A project manager is in the Initiation Stage and has drafted the Project Initiation Documentation. The project board has requested that the document include a summary of the project's justification, including expected benefits and risks. Which component of the Project Initiation Documentation should contain this information?

⚠ Common exam trap

The trap here is assuming that the Risk Management Strategy contains the summary of risks for justification, but it only defines how risks will be managed, not the overall justification.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Business Case

The Business Case is the PID component that provides the justification for the project, including expected benefits, costs, risks, and timescales. The project board requested a summary of the project's justification, which is exactly what the Business Case contains. Other components like the Project Plan, Risk Management Strategy, and Project Controls do not serve this purpose.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Controls

    Why it's wrong here

    Project Controls describe how the project will be monitored and controlled, including reporting and escalation. They do not include the project's justification or expected benefits. This option is incorrect because it focuses on control mechanisms, not the business rationale.

  • ✓

    Business Case

    Why this is correct

    The Business Case is the component that justifies the project by outlining the reasons, benefits, costs, risks, and timescales. It provides the summary of the project's justification, including expected benefits and risks. Therefore it is the correct component to contain this information, as it directly addresses the rationale.

  • ✗

    Project Plan

    Why it's wrong here

    The Project Plan describes how and when the project's products will be delivered, including activities and resources. It does not contain the justification or expected benefits. Thus this option is incorrect because it focuses on delivery mechanisms, not the business rationale.

  • ✗

    Risk Management Strategy

    Why it's wrong here

    The Risk Management Strategy defines the approach to managing risk, including risk tolerances and procedures. It does not summarise the project's justification or benefits. Therefore this option is wrong because it addresses risk management processes, not the overall business case.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.