A project is using the recommended risk management procedure. After identifying a risk, what is the next step?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Assess

The PRINCE2 risk management procedure steps are: Identify, Assess, Plan, Implement, Communicate. After identification, the next step is to assess the risk (probability and impact).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Plan

    Why it's wrong here

    Planning follows risk assessment (estimate, evaluate), not identification. The procedure's next step after identify is assess. Planning is tempting because it is a distinct PRINCE2 risk activity, and it would be correct once the risk's probability, impact and proximity have been estimated and evaluated.

  • ✗

    Communicate

    Why it's wrong here

    Communicate is a step in the PRINCE2 risk procedure, but it runs alongside the others rather than immediately after identify. It is tempting because communication is genuinely part of risk management, and it would be the right emphasis when stakeholders need ongoing visibility of risks throughout the project.

  • ✓

    Assess

    Why this is correct

    Assessing follows identification in PRINCE2's recommended risk management procedure, covering probability, impact and proximity to produce a risk rating. This satisfies the stem's sequence constraint: the procedure orders identify, then assess, before plan responses and implement. Skipping straight to a response would breach that defined process order.

  • ✗

    Implement

    Why it's wrong here

    Implement is a response action, not the step immediately following identification; the risk must first be assessed for probability and impact. It is tempting because implementation eventually occurs, but PRINCE2 requires assessing, then planning, before implementing a response.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project is using the recommended risk management procedure. After identifying a risk, what is the next step?

hard
  • A.Plan responses
  • B.Communicate the risk
  • ✓ C.Assess the risk
  • D.Implement responses

Why C: The PRINCE2 recommended risk management procedure follows the sequence: Identify, Assess, Plan, Implement, and Communicate. After identifying a risk, the next step is to Assess it — estimating its probability and impact, and evaluating its overall severity to decide whether action is needed.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.