A project is in the middle of Stage 3 when a significant new risk is identified that could impact the project's ability to deliver the Business Case. The Project Manager decides to escalate this to the Project Board. Which PRINCE2 practice is being applied when the Project Manager evaluates the risk and decides on a response?

⚠ Common exam trap

The trap here is assuming that because the risk affects the Business Case, the Business Case practice is being applied, when in fact the evaluation and response to a risk is specifically part of the Risk practice.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Risk practice

The Risk practice is the PRINCE2 practice that covers the identification, assessment, and control of risks. It includes evaluating risks, deciding on responses, and implementing them. In this scenario, the Project Manager is applying the Risk practice by evaluating the new risk and deciding how to respond, which may involve escalating to the Project Board if the risk exceeds tolerances.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Progress practice

    Why it's wrong here

    The Progress practice is concerned with monitoring and reporting progress, and making decisions about whether to continue. While risk escalation is a progress-related activity, the evaluation and response to a risk is specifically part of the Risk practice, not the Progress practice. The Progress practice would track the status of the risk but not decide on the response.

  • ✗

    Change practice

    Why it's wrong here

    The Change practice deals with changes to baselined products and the management of issues and changes. While a new risk might lead to a change, the evaluation and response to a risk is not part of the Change practice. The Change practice would be invoked if the risk response required a change to a baselined product.

  • ✓

    Risk practice

    Why this is correct

    The Risk practice in PRINCE2 covers the identification, assessment, and control of risks. It includes evaluating risks, deciding on responses, and implementing those responses. In this scenario, the Project Manager is applying the Risk practice by evaluating the new risk and deciding how to respond, which may include escalating to the Project Board if the risk exceeds tolerances.

  • ✗

    Business Case practice

    Why it's wrong here

    The Business Case practice focuses on the justification for the project and ensuring it remains viable. While the risk may impact the Business Case, the practice does not cover the evaluation and response to risks. The Business Case practice would be used to assess the impact on the business justification, but not to decide on the risk response itself.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.