Courseiva
PRINCE2 Processes →hardMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

A project is in the Closing a Project process. Which of the following is a required activity before the Project Board can authorize closure?

⚠ Common exam trap

The trap is mixing up closure artifacts with initiation artifacts — candidates pick the PID or Project Plan because they sound like formal documents, but those belong to Initiating a Project, not Closing a Project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Prepare the End Project Report

In the Closing a Project process, the Project Manager must prepare the End Project Report, which summarizes performance against the Project Initiation Documentation, reviews the Business Case, and captures lessons learned. The Project Board reviews this report as part of the 'Authorize Project Closure' activity in Directing a Project before granting closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Conduct a post-project benefits review

    Why it's wrong here

    A post-project benefits review occurs after the project has closed, once the products have been in operational use long enough to measure benefits. Closing a Project instead requires the End Project Report and Lessons Report, so conducting this review now would be premature and outside the process.

  • ✓

    Prepare the End Project Report

    Why this is correct

    The End Project Report is a required output of Closing a Project, summarising performance against the baseline and lessons learned. The Project Board needs it to confirm the project has delivered its products before authorising closure, as mandated by PRINCE2.

  • ✗

    Produce the Project Initiation Documentation

    Why it's wrong here

    The Project Initiation Documentation is produced during Initiating a Project, long before closure, and already underpins the project. Closure instead requires confirming the project has delivered its products and that the Business Case, followed by the End Project Report, is updated and accepted by the Project Board.

  • ✗

    Create the Project Plan

    Why it's wrong here

    The Project Plan is created during Initiating a Project and refined throughout delivery, so it already exists at closure. Closing a Project requires the End Project Report, Lessons Report and confirmation of product acceptance, not the creation of a plan that should have been baselined earlier.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.