PRINCE2F PRINCE2 Processes Practice Question
A project is in the Closing a Project process. Which of the following is a required activity before the Project Board can authorize closure?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Prepare the End Project Report
The CP process includes preparing the End Project Report, Lessons Report, and confirming benefits review arrangements. The Project Board authorizes closure in the DP process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Conduct a post-project benefits review
Why it's wrong here
Benefits reviews are planned in CP but conducted after project closure.
- ✓
Prepare the End Project Report
Why this is correct
The End Project Report is a key output of CP, summarizing project performance and providing a recommendation for closure.
- ✗
Produce the Project Initiation Documentation
Why it's wrong here
PID is produced in Initiating a Project, not in closure.
- ✗
Create the Project Plan
Why it's wrong here
The Project Plan is created during Initiating a Project and updated throughout the project.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.