PRINCE2 Processes →mediumMultiple Select

PRINCE2F PRINCE2 Processes Practice Question

A project is in the 'Closing a Project' process. The Project Manager is preparing for the project closure. Which TWO activities are part of this process? (Choose two.)

⚠ Common exam trap

The trap here is mixing activities from Controlling a Stage, such as Take Corrective Action, with those from Closing a Project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Hand Over Products

Closing a Project includes activities such as Prepare Planned Closure and Hand Over Products. These ensure that the project is closed in a controlled manner, with products delivered and accepted, and operational support in place. Take Corrective Action and Authorize a Work Package belong to Controlling a Stage, while Assess Project Benefits is not a closure activity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Assess Project Benefits

    Why it's wrong here

    Assess Project Benefits is not an activity in Closing a Project. Benefits are typically assessed in the Benefits Review Plan, which may be executed after project closure. Closing a Project focuses on confirming closure, handing over products, and evaluating the project.

  • ✓

    Hand Over Products

    Why this is correct

    Hand Over Products is an activity in Closing a Project. It ensures that the project's products are transferred to the operational environment and that necessary support arrangements are in place. This is a key step before final closure.

  • ✗

    Authorize a Work Package

    Why it's wrong here

    Authorize a Work Package is an activity in Controlling a Stage. It involves the Project Manager formally authorizing the Team Manager to start work. It is not part of Closing a Project, which focuses on finalizing the project.

  • ✗

    Take Corrective Action

    Why it's wrong here

    Take Corrective Action is an activity within Controlling a Stage, not Closing a Project. It involves addressing issues and deviations during a stage to keep the stage on track. It is not part of the closure process.

  • ✓

    Prepare Planned Closure

    Why this is correct

    Prepare Planned Closure is an activity within Closing a Project. It involves confirming that all products have been delivered and accepted, and that the project has met its objectives. It ensures that the project is ready for closure in a controlled manner.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.