PRINCE2F PRINCE2 Processes Practice Question
A project is in the 'Closing a Project' process. The Project Manager is preparing for the project closure. Which TWO activities are part of this process? (Choose two.)
⚠ Common exam trap
The trap here is mixing activities from Controlling a Stage, such as Take Corrective Action, with those from Closing a Project.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Hand Over Products
Closing a Project includes activities such as Prepare Planned Closure and Hand Over Products. These ensure that the project is closed in a controlled manner, with products delivered and accepted, and operational support in place. Take Corrective Action and Authorize a Work Package belong to Controlling a Stage, while Assess Project Benefits is not a closure activity.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Assess Project Benefits
Why it's wrong here
Assess Project Benefits is not an activity in Closing a Project. Benefits are typically assessed in the Benefits Review Plan, which may be executed after project closure. Closing a Project focuses on confirming closure, handing over products, and evaluating the project.
- ✓
Hand Over Products
Why this is correct
Hand Over Products is an activity in Closing a Project. It ensures that the project's products are transferred to the operational environment and that necessary support arrangements are in place. This is a key step before final closure.
- ✗
Authorize a Work Package
Why it's wrong here
Authorize a Work Package is an activity in Controlling a Stage. It involves the Project Manager formally authorizing the Team Manager to start work. It is not part of Closing a Project, which focuses on finalizing the project.
- ✗
Take Corrective Action
Why it's wrong here
Take Corrective Action is an activity within Controlling a Stage, not Closing a Project. It involves addressing issues and deviations during a stage to keep the stage on track. It is not part of the closure process.
- ✓
Prepare Planned Closure
Why this is correct
Prepare Planned Closure is an activity within Closing a Project. It involves confirming that all products have been delivered and accepted, and that the project has met its objectives. It ensures that the project is ready for closure in a controlled manner.
Go deeper
Related to this question
About these practice questions
One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.