PRINCE2F People: organizations, teams, and leadership Practice Question

A project is being delivered using PRINCE2. The Project Board has delegated authority to a Change Authority for changes within a defined tolerance. A Request for Change (RFC) is submitted that would impact the project's Business Case and exceed the delegated tolerance. Who should make the decision on this RFC?

⚠ Common exam trap

The trap here is assuming that the Change Authority can approve any change once delegated, ignoring the tolerance limits and the impact on the Business Case.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Project Board, because the change exceeds the delegated tolerance and impacts the Business Case.

The Project Board is accountable for the project and sets tolerances. When a change exceeds the delegated tolerance or impacts the Business Case, the decision must be escalated to the Project Board. The Change Authority only handles changes within its delegated limits. The Project Manager manages the process but does not approve changes beyond tolerance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Change Authority, because it has been delegated authority for all changes.

    Why it's wrong here

    The Change Authority only has authority for changes within the delegated tolerance. Since this RFC exceeds that tolerance and impacts the Business Case, it must be escalated to the Project Board. The Change Authority cannot approve changes beyond its delegated limits.

  • ✓

    The Project Board, because the change exceeds the delegated tolerance and impacts the Business Case.

    Why this is correct

    The Project Board is accountable for the project and retains authority for changes that exceed delegated tolerances or affect the Business Case. Since the RFC exceeds the Change Authority's tolerance and impacts the Business Case, the Project Board must decide whether to approve, reject, or defer the change.

  • ✗

    The Project Manager, because they are responsible for day-to-day management of changes.

    Why it's wrong here

    The Project Manager manages the change control process but does not have authority to approve changes that exceed the delegated tolerance or impact the Business Case. Such changes must be escalated to the Project Board for a decision.

  • ✗

    The Senior User, because they represent the user community and the change affects them.

    Why it's wrong here

    The Senior User is responsible for ensuring the project meets user needs, but they do not have unilateral authority to approve changes. Decisions on changes beyond delegated tolerance are made collectively by the Project Board, not by an individual member.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.