A PRINCE2 project is in the Initiating a Project process. The Project Manager is preparing the Project Initiation Documentation (PID). Which of the following is NOT a component of the PID?

⚠ Common exam trap

The trap here is assuming that the first Stage Plan is part of the PID because it is created during Initiating a Project, when in fact it is a separate document.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Stage Plan

The PID includes the Business Case, Project Plan, Risk Management Approach, and other strategies, but it does not include Stage Plans. Stage Plans are separate documents created for each management stage. The first Stage Plan is developed during Initiating a Project, but it is not part of the PID itself. Therefore, Stage Plan is the correct answer.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Plan

    Why it's wrong here

    The Project Plan is a key component of the PID. It provides a high-level plan for the entire project, including the project's products, activities, resources, and tolerances. It is used to monitor and control the project at the strategic level. It is definitely part of the PID, so it is not the correct answer.

  • ✓

    Stage Plan

    Why this is correct

    A Stage Plan is not a component of the PID. The PID contains the Project Plan, which covers the entire project at a high level. Stage Plans are created for each management stage and are not part of the PID. The first Stage Plan is produced during Initiating a Project, but it is a separate document. Therefore, Stage Plan is the correct answer as it is NOT a component of the PID.

  • ✗

    Risk Management Approach

    Why it's wrong here

    The Risk Management Approach is a component of the PID. It defines how risk will be managed throughout the project, including procedures, roles, and responsibilities. It is one of the strategies included in the PID. Thus, it is not the correct answer to the question.

  • ✗

    Business Case

    Why it's wrong here

    The Business Case is a core component of the PID. It justifies the project by outlining the business need, expected benefits, costs, risks, and timescales. It is updated throughout the project and is essential for the Project Board's continued investment decision. Therefore, it is not the correct answer to the question asking what is NOT a component.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.