A PRINCE2 project is in the Closing a Project process. The Project Manager is preparing for the final closure. Which activity is performed during this process?

⚠ Common exam trap

The trap here is thinking that the Project Manager authorises project closure, when in fact that is a Project Board decision made in Directing a Project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Confirm that all products have been delivered and accepted.

In Closing a Project, the Project Manager confirms that all products have been delivered and accepted according to the quality criteria. This activity ensures that the project has met its objectives and that there are no outstanding issues. The Project Board then authorises project closure based on the End Project Report. Handing over products occurs in Managing Product Delivery, and preparing the next Stage Plan is part of Managing a Stage Boundary.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Authorise the project closure.

    Why it's wrong here

    Authorising project closure is a Project Board activity within the Directing a Project process. The Project Board reviews the End Project Report and gives final approval to close the project. In Closing a Project, the Project Manager prepares the necessary information for this decision, but does not authorise it. This option misassigns the authority.

  • ✓

    Confirm that all products have been delivered and accepted.

    Why this is correct

    Confirming that all products have been delivered and accepted is a key activity in Closing a Project. The Project Manager ensures that all outputs meet the agreed quality criteria and have been formally accepted by the customer or operational environment. This confirmation is essential before the project can be closed, as it verifies that the project has achieved its objectives.

  • ✗

    Prepare the next Stage Plan.

    Why it's wrong here

    Preparing the next Stage Plan is an activity of Managing a Stage Boundary, which occurs at the end of each stage except the final stage. Closing a Project is the final process, so there is no next stage to plan for. This option incorrectly applies a stage boundary activity to project closure.

  • ✗

    Hand over the project's products to the operational environment.

    Why it's wrong here

    Handing over products to the operational environment is part of the Managing Product Delivery process, where work packages are delivered and accepted. In Closing a Project, the focus is on confirming that all products have been handed over and accepted, not performing the handover itself. This option confuses the delivery process with the closure process.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.