PRINCE2-PRACTITIONER Practices Practice Question
In the PRINCE2 Progress practice, what is the name of the report produced by a Team Manager to inform the Project Manager of team-level progress?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Checkpoint Report
A Checkpoint Report is used by Team Managers to report progress on work packages to the Project Manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Highlight Report
Why it's wrong here
Highlight Reports are used by the Project Manager to report to the Project Board.
- ✗
Exception Report
Why it's wrong here
Exception Reports are triggered by forecasted tolerance breaches.
- ✓
Checkpoint Report
Why this is correct
Checkpoint Reports provide team-level progress updates to the Project Manager.
- ✗
End Stage Report
Why it's wrong here
End Stage Reports are produced at stage boundaries for the Project Board.
About these practice questions
This PRINCE2-PRACTITIONER question is part of Courseiva's 297-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.