An organization is executing a high-risk engineering project under PRINCE2 7. The Executive wants to bypass the stage boundary reviews to speed up delivery, arguing that the Business Case is solid. According to PRINCE2, what is the impact of removing management stages?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

It removes vital governance check-points where the Project Board reviews ongoing viability and authorizes continuation.

Removing management stages violates the 'Manage by stages' principle, increasing risk by removing governance checkpoints and control over business justification viability.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • It removes vital governance check-points where the Project Board reviews ongoing viability and authorizes continuation.

    Why this is correct

    Stage boundaries are crucial decision gates for verifying continued business justification and managing risk incrementally.

  • It automatically converts the project into an agile delivery framework.

    Why it's wrong here

    Agile delivery still requires governance stages or iterations; removing stages altogether destroys structured governance.

  • It invalidates the Product Descriptions.

    Why it's wrong here

    Product Descriptions remain valid, but the control and timing of their delivery lack governance checkpoints.

  • It has no impact as long as the Project Manager maintains the Risk Register.

    Why it's wrong here

    Management stages are fundamental to PRINCE2 governance and cannot be omitted without losing key control gates.

About these practice questions

This PRINCE2-PRACTITIONER question is part of Courseiva's 297-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint

This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.