mediumMultiple SelectObjective-mapped
PK0-005 Practice Question: Which TWO of the following are inputs to the…
Which TWO of the following are inputs to the Develop Project Management Plan process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project charter
Inputs to develop the project management plan include the project charter and outputs from other planning processes (subsidiary plans and baselines). Work performance data, change requests, and approved changes are inputs to monitoring and controlling processes.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project charter
Why this is correct
Correct. The charter is an essential input for developing the management plan.
- ✗
Approved change requests
Why it's wrong here
Incorrect. Approved changes are inputs to directing and managing project work, not to plan development.
- ✗
Work performance data
Why it's wrong here
Incorrect. Work performance data is an input to monitoring and controlling processes, not to plan development.
- ✗
Change requests
Why it's wrong here
Incorrect. Change requests are inputs to integrated change control, not to plan development.
- ✓
Outputs from other planning processes
Why this is correct
Correct. Subsidiary plans and baselines from other planning processes are integrated into the overall plan.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.