Which TWO of the following are examples of resource leveling techniques?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Splitting tasks
Resource leveling adjusts the schedule to resolve over-allocation. Delaying tasks and splitting tasks are common leveling techniques. Fast tracking and crashing are schedule compression techniques. Adding resources does not level; it may overload further.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Fast tracking
Why it's wrong here
Fast tracking is schedule compression, not leveling.
- ✓
Splitting tasks
Why this is correct
Splitting tasks allows resources to work on other tasks temporarily.
- ✗
Crashing
Why it's wrong here
Crashing is schedule compression, not leveling.
- ✓
Delaying tasks
Why this is correct
Delaying non-critical tasks can balance resource demand.
- ✗
Adding resources
Why it's wrong here
Adding resources often increases cost and may not solve all allocation issues.
Visual reference
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.