Question 360 of 500
Project Life Cycle PhaseshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is 1 day. This is correct because total float, also known as slack, measures how long a task can be delayed without affecting the overall project finish date, and it is calculated by subtracting the duration of a non-critical path from the duration of the critical path. In this network diagram, the critical path (Path 1) totals 14 days, while Task D lies on Path 2, which totals 13 days, so the total float for Task D is 14 minus 13, equaling 1 day. On the CompTIA Project+ PK0-005 exam, this concept tests your ability to identify the critical path and compute float for tasks on parallel paths, often appearing in exhibit-based questions where you must first determine which path is longest. A common trap is confusing total float with free float or assuming all tasks have float, but remember that only tasks not on the critical path have positive total float. Memory tip: “Float is the gap between the path and the longest lap.”

PK0-005 Project Life Cycle Phases Practice Question

This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Project Network Diagram - Path Durations:
Path 1: Task A (5d) -> Task C (3d) -> Task E (2d) -> Task G (4d) = 14 days
Path 2: Task B (4d) -> Task D (4d) -> Task F (3d) -> Task H (2d) = 13 days
No dependencies between paths.

Refer to the exhibit. What is the total float for Task D?

Question 1hardmultiple choice
Full question →

Exhibit

Project Network Diagram - Path Durations:
Path 1: Task A (5d) -> Task C (3d) -> Task E (2d) -> Task G (4d) = 14 days
Path 2: Task B (4d) -> Task D (4d) -> Task F (3d) -> Task H (2d) = 13 days
No dependencies between paths.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

1 day

The critical path is Path 1 (14 days). Task D is on Path 2 with a duration of 13 days. Total float = critical path duration - non-critical path duration = 14 - 13 = 1 day.

Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 0 days

    Why it's wrong here

    Task D is not on the critical path, so float is not zero.

  • 2 days

    Why it's wrong here

    Incorrect calculation.

  • 3 days

    Why it's wrong here

    Incorrect calculation.

  • 1 day

    Why this is correct

    Float = 14 - 13 = 1 day.

    Related concept

    Static NAT maps one inside address to one outside address.

Common exam traps

Common exam trap: NAT rules depend on direction and matching traffic

NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.

Detailed technical explanation

How to think about this question

NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.

KKey Concepts to Remember

  • Static NAT maps one inside address to one outside address.
  • PAT allows many inside hosts to share one public address using ports.
  • Inside local and inside global describe the private and translated addresses.
  • NAT ACLs identify traffic for translation, not always security filtering.

TExam Day Tips

  • Identify inside and outside interfaces first.
  • Check whether the scenario needs static NAT, dynamic NAT or PAT.
  • Do not confuse NAT matching ACLs with normal packet-filtering intent.

Key takeaway

NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PK0-005 NAT questions on configuration and troubleshooting.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Life Cycle Phases — This question tests Project Life Cycle Phases — Static NAT maps one inside address to one outside address..

What is the correct answer to this question?

The correct answer is: 1 day — The critical path is Path 1 (14 days). Task D is on Path 2 with a duration of 13 days. Total float = critical path duration - non-critical path duration = 14 - 13 = 1 day.

What should I do if I get this PK0-005 question wrong?

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PK0-005 NAT questions on configuration and troubleshooting.

What is the key concept behind this question?

Static NAT maps one inside address to one outside address.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which phase has the most total float?

medium
  • A.Phase B
  • B.Phase A
  • C.Phase D
  • D.Phase C

Why D: Phase D is correct because in a typical project schedule, the phase with the most total float is the one that can be delayed the longest without affecting the project's overall completion date. Total float is calculated as the difference between the late start and early start (or late finish and early finish) of an activity. Phase C has the highest total float value, indicating it has the greatest scheduling flexibility.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.