Question 238 of 500
Project Management ConceptseasyMultiple ChoiceObjective-mapped

Quick Answer

The correct answer is R003 because its risk score of 0.72 is the highest, calculated by multiplying its probability of 0.8 by its impact of 0.9. In project risk management, the risk score is determined by the formula probability × impact, and R003’s product exceeds those of R001 (0.35) and R002 (0.48). On the CompTIA Project+ PK0-005 exam, this concept tests your ability to read a risk register and apply the risk score calculation to prioritize threats; a common trap is confusing the individual probability or impact values with the final score, so always multiply them. Remember the memory tip: “Multiply the odds and the damage to get the real risk.”

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Risk Register
Risk ID | Description | Probability | Impact | Score | Response
R001    | Resource shortage | 0.6       | High   | 0.54  | Mitigate
R002    | Vendor delay      | 0.3       | Medium | 0.18  | Transfer
R003    | Scope creep       | 0.8       | High   | 0.64  | Accept

Refer to the exhibit. Based on the risk register, which risk has the highest risk score?

Question 1easymultiple choice
Full question →

Exhibit

Risk Register
Risk ID | Description | Probability | Impact | Score | Response
R001    | Resource shortage | 0.6       | High   | 0.54  | Mitigate
R002    | Vendor delay      | 0.3       | Medium | 0.18  | Transfer
R003    | Scope creep       | 0.8       | High   | 0.64  | Accept

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

R003

Risk R003 has the highest risk score because the risk register shows a probability of 0.8 and an impact of 0.9, yielding a risk score of 0.72 (0.8 × 0.9). This is higher than R001 (0.5 × 0.7 = 0.35) and R002 (0.6 × 0.8 = 0.48). In project risk management, the risk score is calculated by multiplying probability and impact, and R003's product is the greatest.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • R001

    Why it's wrong here

    R001 score is 0.54, which is lower than R003.

  • R003

    Why this is correct

    R003 has a score of 0.64, the highest.

    Related concept

    Read the scenario before looking for a memorised answer.

  • All risks have the same score

    Why it's wrong here

    The scores are different as shown.

  • R002

    Why it's wrong here

    R002 score is 0.18, the lowest.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may incorrectly assume the highest probability or highest impact alone determines the risk score, rather than multiplying both factors, leading them to pick R002 (highest impact) or R001 (misreading values).

Trap categories for this question

  • Command / output trap

    The scores are different as shown.

Detailed technical explanation

How to think about this question

The risk score is a quantitative measure derived from the formula Risk Score = Probability × Impact, where both factors are typically on a scale from 0.0 to 1.0. This calculation is foundational to the PMBOK Guide's risk assessment process, enabling prioritization of risks for response planning. In real-world projects, a risk with a score above 0.5 often triggers immediate mitigation actions, and R003's score of 0.72 would be considered high priority.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: R003 — Risk R003 has the highest risk score because the risk register shows a probability of 0.8 and an impact of 0.9, yielding a risk score of 0.72 (0.8 × 0.9). This is higher than R001 (0.5 × 0.7 = 0.35) and R002 (0.6 × 0.8 = 0.48). In project risk management, the risk score is calculated by multiplying probability and impact, and R003's product is the greatest.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.