- A
Add more resources
Why wrong: Adding resources may increase cost and is not always feasible; resource leveling is typically preferred.
- B
Outsource the work
Why wrong: Outsourcing may be an option but is not the first action to resolve overallocation.
- C
Apply resource leveling
Resource leveling adjusts the schedule to resolve overallocation without adding resources.
- D
Reduce project scope
Why wrong: Reducing scope is a drastic measure and should be considered only after other options.
Quick Answer
The correct answer is to apply resource leveling. This technique resolves overallocation by delaying tasks within their available float, smoothing demand for a specific resource without extending the project’s critical path. On the CompTIA Project+ PK0-005 exam, this concept tests your ability to distinguish between resource leveling and resource smoothing—a common trap where smoothing adjusts activities only within their float but does not fix overallocation, while leveling actively delays tasks to balance resource loads. Remember that resource leveling is the go-to move when a key resource is overloaded during execution, as it prioritizes resource constraints over schedule flexibility. A helpful memory tip: “Leveling lets you delay, smoothing just shifts—if a resource is overloaded, leveling is the gift.”
PK0-005 Project Life Cycle Phases Practice Question
This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project is in execution, and the project manager discovers that a key resource is overallocated. Which of the following actions should the project manager take to resolve this?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Apply resource leveling
Resource leveling is a technique to address resource overallocation by delaying tasks within their float.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Add more resources
Why it's wrong here
Adding resources may increase cost and is not always feasible; resource leveling is typically preferred.
- ✗
Outsource the work
Why it's wrong here
Outsourcing may be an option but is not the first action to resolve overallocation.
- ✓
Apply resource leveling
Why this is correct
Resource leveling adjusts the schedule to resolve overallocation without adding resources.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Reduce project scope
Why it's wrong here
Reducing scope is a drastic measure and should be considered only after other options.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Project Life Cycle Phases — study guide chapter
Learn the concepts, then practise the questions
- →
Project Life Cycle Phases practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Apply resource leveling — Resource leveling is a technique to address resource overallocation by delaying tasks within their float.
What should I do if I get this PK0-005 question wrong?
Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO of the following are examples of resource leveling techniques?
hard- A.Fast tracking
- ✓ B.Splitting tasks
- C.Crashing
- ✓ D.Delaying tasks
- E.Adding resources
Why B: Resource leveling adjusts the schedule to resolve over-allocation. Delaying tasks and splitting tasks are common leveling techniques. Fast tracking and crashing are schedule compression techniques. Adding resources does not level; it may overload further.
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.