Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: Refer to the exhibit

Exhibit

Task A: Start 1/1, Duration 5d, No Predecessor
Task B: Start 1/6, Duration 3d, Predecessor: A
Task C: Start 1/6, Duration 4d, Predecessor: A
Task D: Start 1/10, Duration 2d, Predecessor: B, C
Task E: Start 1/12, Duration 1d, Predecessor: D
Milestone M1: End of Task E

Refer to the exhibit. What is the critical path duration?

⚠ Common exam trap

Many exam-takers assume the path with the most activities or the largest individual activity durations is the critical path, but they must sum all durations along each complete path from start to end to find the true longest path.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

12 days

The critical path is the longest path through the project network diagram, determining the minimum project duration. Based on the exhibit, the valid paths are: Start→A→C→F→End = 3 + 4 + 5 = 12 days; Start→B→E→End = 2 + 7 = 9 days. Other paths are shorter. Therefore, the critical path duration is 12 days, making option D correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 10 days

    Why it's wrong here

    This path sums to 10 days, which is shorter than the critical path. The critical path is the longest path.

  • 11 days

    Why it's wrong here

    This path sums to 11 days, but the correct critical path is 12 days.

  • 13 days

    Why it's wrong here

    This path sums to 13 days, likely incorrectly including an activity not on any complete path.

  • 12 days

    Why this is correct

    The critical path is Start→A→C→F→End with a duration of 3+4+5=12 days. This is the longest path through the network.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.