- A
RAID controller
Why wrong: RAID controllers provide disk redundancy but are not typically duplicated as components.
- B
Server chassis
Why wrong: Server chassis are not redundant; servers themselves may be clustered.
- C
Power supply
Redundant power supplies ensure continued operation if one fails.
- D
UPS
Redundant UPS units ensure backup power if one unit fails.
- E
Network switch
Redundant switches prevent network outages from a single switch failure.
Quick Answer
The answer is redundant power supplies, redundant network switches, and redundant cooling systems. These three components are critical because a single point of failure in any of them can bring down an entire data center, directly undermining high availability for critical systems. Power supply redundancy, often deployed in N+1 or 2N configurations, ensures uninterrupted operation if a unit fails, while redundant network switches prevent connectivity loss, and redundant cooling prevents thermal shutdown. On the CompTIA Project+ PK0-005 exam, this concept tests your understanding of risk mitigation and business continuity planning for infrastructure projects. A common trap is to overlook cooling as a critical system, focusing only on power and networking; remember that heat is the silent killer of uptime. For a quick memory tip, think “P-N-C” for Power, Network, and Cooling—the three pillars of data center redundancy.
PK0-005 Practice Question: Basics of IT Infrastructure and IT Project Management
This PK0-005 practice question tests your understanding of basics of it infrastructure and it project management. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A data center upgrade project requires redundancy for critical systems. Which three components should be redundant? (Choose three.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Power supply
Power supply redundancy ensures that if one unit fails, the other can sustain the load without downtime. In a data center upgrade, redundant power supplies (often N+1 or 2N configuration) are critical to maintain uptime for servers and network gear. This directly supports high availability for the project's critical systems.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
RAID controller
Why it's wrong here
RAID controllers provide disk redundancy but are not typically duplicated as components.
- ✗
Server chassis
Why it's wrong here
Server chassis are not redundant; servers themselves may be clustered.
- ✓
Power supply
Why this is correct
Redundant power supplies ensure continued operation if one fails.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
UPS
Why this is correct
Redundant UPS units ensure backup power if one unit fails.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Network switch
Why this is correct
Redundant switches prevent network outages from a single switch failure.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may confuse component-level redundancy (like RAID for disks) with infrastructure-level redundancy (power, UPS, network), leading them to select RAID controller or server chassis instead of the correct triad of power, UPS, and network switch.
Detailed technical explanation
How to think about this question
Redundant power supplies typically operate in active/active or active/standby mode, with load sharing via current-sharing circuits. UPS redundancy often uses a parallel configuration with static transfer switches (STS) to ensure seamless failover within milliseconds. Network switch redundancy is achieved through protocols like Spanning Tree Protocol (STP) or Virtual Router Redundancy Protocol (VRRP) to prevent loops and provide failover at Layer 2 or Layer 3.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Basics of IT Infrastructure and IT Project Management — study guide chapter
Learn the concepts, then practise the questions
- →
Basics of IT Infrastructure and IT Project Management practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Basics of IT Infrastructure and IT Project Management — This question tests Basics of IT Infrastructure and IT Project Management — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Power supply — Power supply redundancy ensures that if one unit fails, the other can sustain the load without downtime. In a data center upgrade, redundant power supplies (often N+1 or 2N configuration) are critical to maintain uptime for servers and network gear. This directly supports high availability for the project's critical systems.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.