Question 235 of 500
Project Management ConceptseasyMultiple SelectObjective-mapped

Quick Answer

The answer is the scope baseline, schedule baseline, and cost baseline. These three form the core baseline trio of a project management plan because each represents an approved, formally controlled version of a key constraint—scope, time, and cost—against which actual project performance is measured and managed. On the CompTIA Project+ PK0-005 exam, this concept tests your understanding that baselines are not optional; they are the fixed reference points for tracking variance and controlling changes through integrated change control. A common trap is confusing subsidiary plans (like the risk or quality plan) with baselines, but remember: only scope, schedule, and cost have baselines that are formally approved and frozen. A helpful memory tip is the “Triple Baseline Triangle”—scope, schedule, and cost are the three legs that support every project management plan.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which THREE of the following are key components of a project management plan?

Question 1easymulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule baseline

The schedule baseline (A) is a key component of the project management plan because it is the approved version of the project schedule that serves as a reference against which actual performance is measured. It includes start and end dates for activities, milestones, and dependencies, and is part of the project management plan's baseline trio. Without the schedule baseline, there is no formal benchmark for tracking schedule variance or managing changes.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Schedule baseline

    Why this is correct

    Schedule baseline is the approved project schedule.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Risk register

    Why it's wrong here

    Risk register is a separate document, not part of PM plan.

  • Cost baseline

    Why this is correct

    Cost baseline is the approved budget.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Scope baseline

    Why this is correct

    Scope baseline is approved scope statement, WBS, WBS dictionary.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Issue log

    Why it's wrong here

    Issue log is a project document, not part of PM plan.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Cisco often tests the distinction between 'components of the project management plan' (baselines and subsidiary plans) and 'project documents' (risk register, issue log, stakeholder register) to see if candidates confuse operational artifacts with formal planning components.

Detailed technical explanation

How to think about this question

The project management plan is a formal, approved document that defines how the project is executed, monitored, and controlled. Its key components include the scope baseline (scope statement, WBS, WBS dictionary), schedule baseline (schedule model with approved start/finish dates), and cost baseline (time-phased budget). These baselines are controlled through integrated change control, and any deviation requires a formal change request. In real-world scenarios, failing to distinguish between baselines and project documents leads to scope creep and uncontrolled cost overruns.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Schedule baseline — The schedule baseline (A) is a key component of the project management plan because it is the approved version of the project schedule that serves as a reference against which actual performance is measured. It includes start and end dates for activities, milestones, and dependencies, and is part of the project management plan's baseline trio. Without the schedule baseline, there is no formal benchmark for tracking schedule variance or managing changes.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

4 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which THREE of the following are components of the project management plan as defined in the PMBOK Guide?

medium
  • A.Project charter
  • B.Schedule baseline
  • C.Risk register
  • D.Cost baseline
  • E.Scope baseline

Why B: The schedule baseline (B) is a component of the project management plan because it is an approved version of the schedule model that is used as a basis for comparison to actual results. The PMBOK Guide defines the project management plan as including baselines such as the schedule, cost, and scope baselines, which are used to measure project performance.

Variation 2. Which TWO of the following are components of the project management plan?

medium
  • A.Project charter
  • B.Scope baseline
  • C.Schedule baseline
  • D.Stakeholder register
  • E.Risk register

Why B: The project management plan is the formal, approved document that defines how the project is executed, monitored, and controlled. The scope baseline (which includes the scope statement, WBS, and WBS dictionary) and the schedule baseline (which includes the approved schedule model) are key components of this plan, as they establish the performance measurement baselines against which project progress is measured.

Variation 3. Which TWO of the following are components of the project management plan?

medium
  • A.Risk register
  • B.Issue log
  • C.Stakeholder register
  • D.Scope baseline
  • E.Schedule baseline

Why D: The scope baseline and schedule baseline are formal, approved components of the project management plan. The scope baseline consists of the scope statement, Work Breakdown Structure (WBS), and WBS dictionary, while the schedule baseline is the approved version of the project schedule. Both are essential for measuring and controlling project performance.

Variation 4. A project manager is reviewing the key components of a project management plan. Which THREE of the following are typically included in a project management plan?

hard
  • A.Risk register
  • B.Issue log
  • C.Schedule baseline
  • D.Cost baseline
  • E.Scope baseline

Why C: The schedule baseline (C) is a key component of the project management plan because it is the approved version of the project schedule that serves as a reference point against which actual progress is measured. It includes start and end dates for activities, milestones, and dependencies, and any changes to it must go through formal change control.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.