Courseiva
hardMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project manager is using a prioritized list of…

A project manager is using a prioritized list of project risks. Each risk has an assigned owner and a planned response. The project manager notices that one risk has a high probability and impact, but no response has been planned. What should the project manager do FIRST?

⚠ Common exam trap

Many exam-takers confuse the risk register with the issue log or assume that escalation is always the first step for high-impact risks, but the PMI methodology requires the project manager to first attempt to plan a response within their authority before escalating.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Develop a risk response and update the risk register

The project manager should first develop a risk response and update the risk register because a high-probability, high-impact risk without a planned response represents a critical gap in proactive risk management. The risk register is the central repository for tracking risks, their owners, and responses; failing to document a response leaves the project exposed to unmitigated threats. This aligns with the PMBOK Guide's iterative risk management process, where identified risks must have responses planned and recorded before they can be effectively monitored or controlled.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Develop a risk response and update the risk register

    Why this is correct

    The risk register must be updated with a response to address the risk.

  • Escalate the risk to the project sponsor

    Why it's wrong here

    Escalation should occur after a response is developed or if outside authority is needed.

  • Review the risk management plan for guidance

    Why it's wrong here

    The risk management plan provides processes, not specific responses.

  • Add the risk to the issue log

    Why it's wrong here

    An issue is a problem that has occurred; this risk has not yet occurred.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.