- A
Develop a risk response and update the risk register
The risk register must be updated with a response to address the risk.
- B
Escalate the risk to the project sponsor
Why wrong: Escalation should occur after a response is developed or if outside authority is needed.
- C
Review the risk management plan for guidance
Why wrong: The risk management plan provides processes, not specific responses.
- D
Add the risk to the issue log
Why wrong: An issue is a problem that has occurred; this risk has not yet occurred.
Quick Answer
The correct first step is to develop a risk response and update the risk register. This is because a high-impact, high-probability risk without a planned response represents a critical gap in proactive risk management; the risk register is the central repository for tracking risks, owners, and responses, and failing to document a response leaves the project exposed to unmitigated threats. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of the iterative risk management process, where risk response planning must occur before monitoring and controlling can begin. A common trap is to jump to escalating the risk or adding it to a watch list, but the immediate priority is to create and record a response for any high-priority risk that lacks one. Memory tip: think “No plan, no control”—if a high-impact risk has no response planned, you must first plan it and log it in the register before you can do anything else.
PK0-005 Tools and Documentation Practice Question
This PK0-005 practice question tests your understanding of tools and documentation. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is using a prioritized list of project risks. Each risk has an assigned owner and a planned response. The project manager notices that one risk has a high probability and impact, but no response has been planned. What should the project manager do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Develop a risk response and update the risk register
The project manager should first develop a risk response and update the risk register because a high-probability, high-impact risk without a planned response represents a critical gap in proactive risk management. The risk register is the central repository for tracking risks, their owners, and responses; failing to document a response leaves the project exposed to unmitigated threats. This aligns with the PMBOK Guide's iterative risk management process, where identified risks must have responses planned and recorded before they can be effectively monitored or controlled.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Develop a risk response and update the risk register
Why this is correct
The risk register must be updated with a response to address the risk.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Escalate the risk to the project sponsor
Why it's wrong here
Escalation should occur after a response is developed or if outside authority is needed.
- ✗
Review the risk management plan for guidance
Why it's wrong here
The risk management plan provides processes, not specific responses.
- ✗
Add the risk to the issue log
Why it's wrong here
An issue is a problem that has occurred; this risk has not yet occurred.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse the risk register with the issue log or assume that escalation is always the first step for high-impact risks, but the PMI methodology requires the project manager to first attempt to plan a response within their authority before escalating.
Detailed technical explanation
How to think about this question
In the PK0-005 context, the risk register is a living document that includes fields for risk ID, description, probability, impact, risk score, owner, and response strategy. When a high-priority risk lacks a response, the project manager must apply the appropriate response strategy (e.g., avoid, mitigate, transfer, accept) and update the register with the planned actions and contingency reserves if needed. A real-world scenario might involve a critical vendor dependency risk: without a documented response (e.g., identifying an alternative vendor), the project could face schedule delays that cascade into unplanned costs, highlighting why immediate documentation is essential for risk tracking and audit trails.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Tools and Documentation — study guide chapter
Learn the concepts, then practise the questions
- →
Tools and Documentation practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Develop a risk response and update the risk register — The project manager should first develop a risk response and update the risk register because a high-probability, high-impact risk without a planned response represents a critical gap in proactive risk management. The risk register is the central repository for tracking risks, their owners, and responses; failing to document a response leaves the project exposed to unmitigated threats. This aligns with the PMBOK Guide's iterative risk management process, where identified risks must have responses planned and recorded before they can be effectively monitored or controlled.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.