- A
FS, FS, SS
First two are FS, third is SS.
- B
SS, SS, SS
Why wrong: Only the last is SS.
- C
FS, FS, SF
Why wrong: SF is Start-to-Finish, not applicable.
- D
FS, FF, SS
Why wrong: FF is Finish-to-Finish, not used.
Quick Answer
The correct answer is FS, FS, SS because the three dependency types described map exactly to Finish-to-Start, Finish-to-Start, and Start-to-Start. In project schedule dependency types, a Finish-to-Start (FS) relationship means a successor task cannot begin until its predecessor has finished, which applies to both “Task A starts after Task B finishes” and “Task C must be completed before Task D can start.” The third dependency, “Task E can start when Task F starts,” is a Start-to-Start (SS) relationship, where both tasks can begin simultaneously. On the CompTIA Project+ PK0-005 exam, you will often see these dependency types tested in scenario-based questions that require you to identify the correct relationship from plain-language descriptions. A common trap is confusing FS with SS when the wording uses “after” or “when,” so focus on whether the trigger is the finish or the start of the predecessor. Remember the mnemonic: “Finish-to-Start is the classic handoff; Start-to-Start means they kick off together.”
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is developing the project schedule. Dependencies include: Task A starts after Task B finishes; Task C must be completed before Task D can start; Task E can start when Task F starts. Which dependency types are being used?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
FS, FS, SS
Option A is correct because the three dependency types described map exactly to Finish-to-Start (FS), Finish-to-Start (FS), and Start-to-Start (SS). 'Task A starts after Task B finishes' is FS; 'Task C must be completed before Task D can start' is also FS; 'Task E can start when Task F starts' is SS. These are the standard dependency definitions used in project scheduling per PMI guidelines.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
FS, FS, SS
Why this is correct
First two are FS, third is SS.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
SS, SS, SS
Why it's wrong here
Only the last is SS.
- ✗
FS, FS, SF
Why it's wrong here
SF is Start-to-Finish, not applicable.
- ✗
FS, FF, SS
Why it's wrong here
FF is Finish-to-Finish, not used.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse 'starts after finishes' with Start-to-Start (SS) or Start-to-Finish (SF), failing to recognize that 'starts after' implies the predecessor must finish first, which is the definition of Finish-to-Start (FS).
Detailed technical explanation
How to think about this question
In project scheduling, dependency types define the logical relationship between tasks. FS is the most common, used for sequential tasks where the successor cannot start until the predecessor finishes. SS allows parallel execution, often used for overlapping phases (e.g., design and coding). A subtle behavior: SS can have a lag or lead time applied, such as 'Task E starts 2 days after Task F starts,' which is still an SS dependency with a positive lag. Real-world scenario: in software development, testing (Task E) might start when coding (Task F) begins, using SS to enable early defect detection.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: FS, FS, SS — Option A is correct because the three dependency types described map exactly to Finish-to-Start (FS), Finish-to-Start (FS), and Start-to-Start (SS). 'Task A starts after Task B finishes' is FS; 'Task C must be completed before Task D can start' is also FS; 'Task E can start when Task F starts' is SS. These are the standard dependency definitions used in project scheduling per PMI guidelines.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.