- A
Obtain formal approval of the project charter.
Why wrong: Charter approval is part of initiation.
- B
Create the risk management plan.
Risk planning is a key planning activity.
- C
Monitor and control project work.
Why wrong: Monitoring is part of monitoring and controlling.
- D
Collect requirements from stakeholders.
Why wrong: Requirements collection is typically in initiation or early planning, but not a key planning activity listed here.
- E
Develop the project schedule.
Schedule development is a planning activity.
Quick Answer
The answer is developing the project schedule and creating the risk management plan. These are key activities during the planning phase because this phase transforms the project charter into actionable blueprints: the schedule sequences tasks and allocates resources to meet deadlines, while the risk management plan proactively identifies threats and documents response strategies to avoid surprises later. On the CompTIA Project+ PK0-005 exam, this question tests your ability to distinguish planning phase outputs from those of executing or closing phases—a common trap is confusing risk identification (planning) with risk response implementation (executing). Remember the memory tip: “Plan the work before you work the plan”—if an activity creates a document or baseline for future work, it belongs in planning.
PK0-005 Project Life Cycle Phases Practice Question
This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO of the following are key activities typically performed during the planning phase of a project? (Choose two.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Create the risk management plan.
The planning phase involves developing detailed plans to guide project execution. Creating the risk management plan (B) is a key planning activity because it identifies, analyzes, and documents risk response strategies. Developing the project schedule (E) is also a core planning activity, as it sequences tasks, assigns resources, and establishes timelines for project deliverables.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Obtain formal approval of the project charter.
Why it's wrong here
Charter approval is part of initiation.
- ✓
Create the risk management plan.
Why this is correct
Risk planning is a key planning activity.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Monitor and control project work.
Why it's wrong here
Monitoring is part of monitoring and controlling.
- ✗
Collect requirements from stakeholders.
Why it's wrong here
Requirements collection is typically in initiation or early planning, but not a key planning activity listed here.
- ✓
Develop the project schedule.
Why this is correct
Schedule development is a planning activity.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Cisco often tests the distinction between initiating and planning phase activities, so the trap here is confusing the project charter approval (initiating) with planning activities like risk management and schedule development, or mistaking requirements collection as not being a planning activity when it actually is, but it is not one of the two correct answers in this specific question.
Detailed technical explanation
How to think about this question
During the planning phase, the project management plan is developed as a comprehensive document that integrates subsidiary plans such as the risk management plan and the schedule management plan. The risk management plan defines how risk identification, qualitative and quantitative analysis, response planning, and monitoring will be structured. The project schedule is built using techniques like critical path method (CPM) and precedence diagramming method (PDM), often with tools like Microsoft Project or Jira, and must account for dependencies, resource availability, and buffers.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Life Cycle Phases — study guide chapter
Learn the concepts, then practise the questions
- →
Project Life Cycle Phases practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Create the risk management plan. — The planning phase involves developing detailed plans to guide project execution. Creating the risk management plan (B) is a key planning activity because it identifies, analyzes, and documents risk response strategies. Developing the project schedule (E) is also a core planning activity, as it sequences tasks, assigns resources, and establishes timelines for project deliverables.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 11, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.