- A
Lessons learned register
Why wrong: Lessons learned are documented throughout but formally finalized in Closing.
- B
Work performance data
Work performance data is collected during execution for monitoring purposes.
- C
Change requests
Change requests can arise from execution and feed into monitoring and controlling.
- D
Project management plan
Why wrong: The project management plan is developed in Planning, not executed.
- E
Deliverables
Deliverables are the primary outputs of executing processes.
Quick Answer
The answer is deliverables, along with work performance data and change requests. These are the three key outputs of the Executing phase because this is where the project team actively performs the work defined in the project management plan to create the product, service, or result. Work performance data is generated as raw observations and measurements during task execution, while change requests arise when issues or variances require adjustments to the plan or scope. On the CompTIA Project+ PK0-005 exam, this concept tests your ability to distinguish phase outputs from inputs—a common trap is confusing the project management plan, which is an output of Planning, with Executing outputs. Another frequent pitfall is associating the lessons learned register with Executing, but it is formally updated during Closing. To remember this, think of the Executing phase as the "do" phase: you do the work (deliverables), you do the tracking (work performance data), and you do the fixes (change requests). A handy mnemonic is "DWC"—Deliverables, Work data, Changes.
PK0-005 Project Life Cycle Phases Practice Question
This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which THREE of the following are key outputs of the Executing phase?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Work performance data
During Executing, the project team produces deliverables, work performance data is collected, and change requests may arise. The project management plan is an output of Planning, and the lessons learned register is updated in Closing.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Lessons learned register
Why it's wrong here
Lessons learned are documented throughout but formally finalized in Closing.
- ✓
Work performance data
Why this is correct
Work performance data is collected during execution for monitoring purposes.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Change requests
Why this is correct
Change requests can arise from execution and feed into monitoring and controlling.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Project management plan
Why it's wrong here
The project management plan is developed in Planning, not executed.
- ✓
Deliverables
Why this is correct
Deliverables are the primary outputs of executing processes.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Project Life Cycle Phases — study guide chapter
Learn the concepts, then practise the questions
- →
Project Life Cycle Phases practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Work performance data — During Executing, the project team produces deliverables, work performance data is collected, and change requests may arise. The project management plan is an output of Planning, and the lessons learned register is updated in Closing.
What should I do if I get this PK0-005 question wrong?
Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.