Question 103 of 500
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is 11 days. This is correct because the total duration of a project is determined by the longest path through the network diagram, known as the critical path, which dictates the earliest possible completion date. In this scenario, both path A → B → D and path A → C → D take 11 days, as activity D cannot start until both B and C finish, with C ending later on day 9, pushing D to finish on day 11. On the CompTIA Project+ PK0-005 exam, this tests your ability to calculate project duration from critical path by identifying dependencies and summing durations along the longest sequence, a core skill for schedule management questions. A common trap is to simply add all activity durations without accounting for parallel tasks or the dependency that forces a later start. Remember the memory tip: “The critical path is the longest line, not the sum of all time.”

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Task | Duration | Dependencies | Start | Finish
A    | 5d       | None         | Day 1 | Day 5
B    | 3d       | A            | Day 6 | Day 8
C    | 4d       | A            | Day 6 | Day 9
D    | 2d       | B,C          | Day 10| Day 11

Refer to the exhibit. What is the total duration of the project?

Question 1mediummultiple choice
Full question →

Exhibit

Task | Duration | Dependencies | Start | Finish
A    | 5d       | None         | Day 1 | Day 5
B    | 3d       | A            | Day 6 | Day 8
C    | 4d       | A            | Day 6 | Day 9
D    | 2d       | B,C          | Day 10| Day 11

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

11 days

The critical path is A → B → D or A → C → D. A takes 5 days (days 1-5). B takes 3 days (days 6-8), C takes 4 days (days 6-9). D depends on both B and C, so it starts after the latest finish (day 9) and finishes on day 11. Thus total duration is 11 days. Option A is correct.

Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 9 days

    Why it's wrong here

    9 days is less than the critical path.

  • 8 days

    Why it's wrong here

    8 days is not possible given the task durations.

  • 14 days

    Why it's wrong here

    This would be if durations were summed without considering dependencies.

  • 11 days

    Why this is correct

    Project starts day 1, ends day 11, total 11 days.

    Related concept

    Static NAT maps one inside address to one outside address.

Common exam traps

Common exam trap: NAT rules depend on direction and matching traffic

NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.

Detailed technical explanation

How to think about this question

NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.

KKey Concepts to Remember

  • Static NAT maps one inside address to one outside address.
  • PAT allows many inside hosts to share one public address using ports.
  • Inside local and inside global describe the private and translated addresses.
  • NAT ACLs identify traffic for translation, not always security filtering.

TExam Day Tips

  • Identify inside and outside interfaces first.
  • Check whether the scenario needs static NAT, dynamic NAT or PAT.
  • Do not confuse NAT matching ACLs with normal packet-filtering intent.

Key takeaway

NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PK0-005 NAT questions on configuration and troubleshooting.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Static NAT maps one inside address to one outside address..

What is the correct answer to this question?

The correct answer is: 11 days — The critical path is A → B → D or A → C → D. A takes 5 days (days 1-5). B takes 3 days (days 6-8), C takes 4 days (days 6-9). D depends on both B and C, so it starts after the latest finish (day 9) and finishes on day 11. Thus total duration is 11 days. Option A is correct.

What should I do if I get this PK0-005 question wrong?

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PK0-005 NAT questions on configuration and troubleshooting.

What is the key concept behind this question?

Static NAT maps one inside address to one outside address.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PK0-005 practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.